Anthropic-Amazon New Carlisle

Also known as Project Rainier

OperatingAI campusCampusNew Carlisle, St. Joseph County, Indiana
90% profile completeness
79 claims from 13 sources
Current facility power
1.09 GW[1]
Likelyestimated
Planned capacity
2.2 GW[2]
ConfirmedDisputed
Building footprint
1.47M sq ft[6]
Likelyderived
Buildings (planned)
30[2]
ConfirmedDisputed
Capital cost / investment
$11B[2]
ConfirmedDisputed
First operational
Oct 2025[2]
LikelyDisputed

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery and news report.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Indiana Michigan Power (AEP) · PJM
Substation: On-site substation

Power reality

Announced
2.2 GW[2]
Reported by CNBC
Interconnection request
No record
Contracted / approved
No record
Under construction
1.22 GW[1]
Buildings 17–18, Buildings 19–32 under construction (satellite-tracked phases)
Operational
1.09 GW[1]
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. AnnouncedOct 29, 2025
    News report
    • Oct 29, 2025 · Planned capacity reported: 2200 MW[2]
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionFeb 9, 2024
    Model estimate · Satellite imagery · News report
    • Feb 9, 2024 · Reported status: under construction[1]
    • Feb 9, 2024 · Construction start[1]
    • Feb 9, 2024 · Land clearing begins in the northern section[1]
    • Sep 2024 · Construction start[2]
    • Jun 23, 2025 · Reported status: expanding[1]
  3. EnergizationJun 23, 2025
    Satellite imagery
    • Jun 23, 2025 · Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.[1]
    • Dec 23, 2025 · Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complet[1]
    • Mar 23, 2026 · Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.[1]
  4. OperationalJun 23, 2025
    Satellite imagery · News report
    • Jun 23, 2025 · Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.[1]
    • Oct 29, 2025 · Reported status: operating[2]
    • Dec 23, 2025 · Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complet[1]
    • Mar 23, 2026 · Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: News report, Model estimate, Satellite imagery.

Grid path

  1. facility
    Anthropic-Amazon New Carlisle
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    4 substation outlines traced inside the campus on satellite imagery
  3. transmission
    345 kV line[6]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.89 km away). Not confirmed as the supply path.
  4. utility
    Indiana Michigan Power (AEP)[2]
    DocumentedLikely
    Named in a source
  5. ISO / RTO
    PJM[4]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
41.67911, -86.47206
Address
55001 Larrison Blvd, New Carlisle, IN 46552[1]Likely
County
St. Joseph County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Operator

“Amazon has opened a data center on 1,200 acres of land in Indiana”

End user

“dedicated to training and running models from Anthropic”

Utility

“working with American Electric Power through its Indiana Michigan Power subsidiary”

Power (all fields)

Current facility power
1.09 GW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
910 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
2.2 GW[2]Confirmed

“draw more than 2.2 gigawatts of electricity” — Lower bound ("more than").

Sources disagree. Also reported: 2.31 GW[1] (likely)
Estimated annual consumption
6,696 GWh/yr[3]Speculativeestimated

1092 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[4]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[5]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (345 kV)[6]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
1.2 km[6]Likelyderived
Highest-voltage line nearby
345 kV[6]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.16¢/kWh[8]Confirmed

Indiana statewide average, July 2026.

State avg. commercial price
13.30¢/kWh[8]Confirmed

Indiana statewide average, July 2026.

Generation within 50 km
4.7 GW[9]Confirmedderived

22 EIA-reported plants within 50 km.

Generation queued in county
2.71 GW[7]Confirmedderived

14 active generation interconnection requests in St. Joseph County: Solar 790 MW, Gas 786 MW, Solar + storage 588 MW, Storage 542 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
345 kV lineTransmission line0.89 km345 kV[6]
St Joseph Energy Center · St Joseph Energy Center LLCPower plant (Natural Gas)2.3 km715 MW[9]
Honeysuckle Solar Farm · Lightsource Renewable Energy Asset Management, LLCPower plant (Solar)4.5 km150 MW[9]
University of Notre Dame · University of Notre DamePower plant (Natural Gas)19.8 km39 MW[9]
Indeck Niles Energy Center · Indeck Niles, LLCPower plant (Natural Gas)29.1 km1.08 GW[9]
St. Joseph Solar · Indiana Michigan Power CoPower plant (Solar)30.7 km20 MW[9]
Donald C Cook · Indiana Michigan Power CoPower plant (Nuclear)33.9 km2.18 GW[9]
Bremen · Indiana Municipal Power AgencyPower plant (Solar)35.2 km7 MW[9]
Michigan City · Northern Indiana Pub Serv CoPower plant (Coal)36.5 km455 MW[9]
Unnamed substationSubstation1.22 km345 kV[6]
Unnamed substationSubstation1.27 km345 kV[6]
Unnamed substationSubstation1.41 km345 kV[6]
Unnamed substationSubstation1.99 km34.5 kV[6]
Edison Substation · AEP OhioSubstation2.35 km138 kV[6]
Elderberry Substation · AEP OhioSubstation2.4 km345 kV[6]
Largest queued generation in this countyFuelQueue statusMWSource
Elderberry 345 kVPJM AG2-562GasIn study · proposed 2022-10786 MW[7]
Olive - Dumont 345 kVPJM AH2-112Solar + storageIn study · proposed 2026-02250 MW[7]
Northern St. Joseph 138 kVPJM AH2-347StorageIn study · proposed 2025-03200 MW[7]
New Carlisle 138 kVPJM AH1-479StorageIn study · proposed 2023-09192 MW[7]
Honeysuckle Solar ProjectPJM AF1-158Solar + storageUnder construction · proposed 2025-01150 MW[7]
Dumont 345 kVPJM AG2-230SolarIn study · proposed 2024-12150 MW[7]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Sep 2024[2]
  5. First operational
    Oct 2025[2]
  6. Expected completion
    Mar 17, 2028[1]
    Projected
Planned capacity
2.2 GW[2]Confirmed

“draw more than 2.2 gigawatts of electricity” — Lower bound ("more than").

Sources disagree. Also reported: 2.31 GW[1] (likely)
Buildings (planned)
30[2]Confirmed

“The full site will eventually span 30 buildings”

Sources disagree. Also reported: 18[1] (likely)
Buildings operational
7[2]Confirmed

“as of this month, seven buildings are already online”

Sources disagree. Also reported: 16[1] (likely)
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–7operational478 MWJun 23, 2025[1]
Buildings 8–11operational273 MWDec 23, 2025[1]
Buildings 12–16operational341 MWMar 23, 2026[1]
Buildings 17–18under construction152 MWOct 19, 2026 (projected)[1]
Buildings 19–32under construction1.07 GWMar 17, 2028 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Site area
1,200 acres[2]Confirmed

“a data center on 1,200 acres of land in Indiana”

Capital cost / investment
$11B[2]Confirmed

“it signed an $11 billion agreement with Indiana, the largest capital investment in the state's history”

Sources disagree. Also reported: $34.5B[1] (likely)
Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
1.47M sq ft[6]Likelyderived

Sum of 7 building outlines mapped in OpenStreetMap within this campus.

Floor area
Not yet sourced

Compute

Project
Project Rainier[1]Confirmed
Chip types
Trainium2[1][2]Confirmed

“Rainier's seven data center buildings are packed wall-to-wall with Trainium 2, Amazon's custom-built chips”

Compute (H100-equivalents)
685,900[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    398 MWJun 23, 2025[1]→626 MWDec 23, 2025[1]→910 MWMar 23, 2026[1]
  • Current facility power
    478 MWJun 23, 2025[1]→751 MWDec 23, 2025[1]→1.09 GWMar 23, 2026[1]
  • Planned capacity
    2.2 GWOct 2025[2]→2.2 GWOct 2025[10]→2.31 GWJun 3, 2026[1]
  • Capital cost / investment
    $11BOct 2025[2]→$11BOct 2025[10]→$34.5BJun 3, 2026[1]
  • Buildings (planned)
    30Oct 2025[2]→30Oct 2025[10]→18Jun 3, 2026[1]
  • Buildings operational
    0Feb 9, 2024[1]→7Jun 23, 2025[1]→7Oct 2025[2]→7Oct 2025[10]→11Dec 23, 2025[1]→16Mar 23, 2026[1]
  • Status
    Under constructionFeb 9, 2024[1]→Operating + expandingJun 23, 2025[1]→OperatingOct 29, 2025[10]→OperatingOct 29, 2025[2]

Timeline

Construction start: Sep 2024[2]
First operational: Oct 2025[2]
  1. Feb 9, 2024[1]

    Land clearing begins in the northern section

  2. Jun 10, 2024[1]

    Land clearing begins in the southern section

  3. May 10, 2025[1]

    Roof complete on building 11

  4. Jun 23, 2025478 MW facility power· 7 buildings operational[1]

    Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.

  5. Sep 26, 2025478 MW facility power· 7 buildings operational[1]

    Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it.

  6. Oct 17, 2025478 MW facility power· 7 buildings operational[1]

    Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an interview, AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today".

  7. Dec 23, 2025751 MW facility power· 11 buildings operational[1]

    Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.

  8. Feb 9, 2026751 MW facility power· 11 buildings operational[1]

    Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape.

  9. Mar 23, 20261.09 GW facility power· 16 buildings operational[1]

    Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.

  10. Jun 3, 20261.09 GW facility power· 16 buildings operational[1]

    Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.

  11. Oct 19, 2026Projected1.24 GW facility power· 18 buildings operational[1]

    Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.

  12. Mar 17, 2028Projected2.31 GW facility power· 32 buildings operational[1]

    Buildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundation of several buildings and a substation was visible at the site of Buildings 19-32. Buildings 1-16 took 1 year and 10 months to go from a similar state to operational. So we add 1 year and 10 months to May 2026 to get this date estimate. The power capacity is based on an air quality permit filed in May 2026, and the compute capacity is based on Trainium3 chips.

Buildings on this campus

1

All claims (provenance audit)

79
FieldValueSourceConfidenceAs ofStatus
NameAnthropic-Amazon New Carlisle[1] Likely2026-06-03Shown
Also known asProject Rainier[2] Confirmed2025-10-29Shown
StatusUnder construction[1] derivedLikely2024-02-09Superseded / alternative
StatusUnder construction[1] derivedLikely2024-06-10Superseded / alternative
StatusUnder construction[1] derivedLikely2025-05-10Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-06-23Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-09-26Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-10-17Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-12-23Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-02-09Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-03-23Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-06-03Superseded / alternative
StatusOperating[2] AI-extractedLikely2025-10-29Shown
Facility typeAI campus[1] derivedLikely2026-06-03Shown
ProjectProject Rainier[1] Confirmed2026-06-03Shown
Address55001 Larrison Blvd, New Carlisle, IN 46552[1] Likely2026-06-03Shown
OwnerAmazon Web ServicesOwner: Amazon[1] Confirmed2026-06-03Shown
OperatorAmazon Web Services[2] AI-extractedLikely2025-10-29Shown
End usersAnthropicUsers: Anthropic[1] Confirmed2026-06-03Shown
End usersAnthropic[2] Confirmed2025-10-29Shown
End usersAnthropic[2] AI-extractedLikely2025-10-29Shown
UtilityIndiana Michigan Power (AEP)[2] Likely2025-10-29Shown
UtilityIndiana Michigan Power (AEP)[2] AI-extractedLikely2025-10-29Shown
Current facility power1.09 GW[1] estimatedLikely2026-06-03Shown
Current facility power478 MW[1] estimatedLikely2025-06-23Superseded / alternative
Current facility power478 MW[1] estimatedLikely2025-09-26Superseded / alternative
Current facility power478 MW[1] estimatedLikely2025-10-17Superseded / alternative
Current facility power751 MW[1] estimatedLikely2025-12-23Superseded / alternative
Current facility power751 MW[1] estimatedLikely2026-02-09Superseded / alternative
Current facility power1.09 GW[1] estimatedLikely2026-03-23Superseded / alternative
Current IT capacity910 MW[1] estimatedLikely2026-06-03Shown
Current IT capacity398 MW[1] estimatedLikely2025-06-23Superseded / alternative
Current IT capacity398 MW[1] estimatedLikely2025-09-26Superseded / alternative
Current IT capacity398 MW[1] estimatedLikely2025-10-17Superseded / alternative
Current IT capacity626 MW[1] estimatedLikely2025-12-23Superseded / alternative
Current IT capacity626 MW[1] estimatedLikely2026-02-09Superseded / alternative
Current IT capacity910 MW[1] estimatedLikely2026-03-23Superseded / alternative
Planned capacity2.31 GW[1] estimatedLikely2026-06-03Superseded / alternative
Planned capacity2.2 GW[2] Confirmed2025-10-29Shown
Planned capacity2.2 GW[2] AI-extractedLikely2025-10Superseded / alternative
Estimated annual consumption6,696 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[4] derivedLikely—Shown
Balancing authorityPJM[5] derivedLikely—Shown
Nearest mapped substationUnnamed substation (345 kV)way/1466907498[6] derivedLikely2026-09-28Shown
Distance to substation1.2 km[6] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[6] derivedLikely2026-09-28Shown
Generation queued in county2.71 GW[7] derivedConfirmed2026-09-27Shown
State avg. industrial price9.16¢/kWh[8] Confirmed2026-07Shown
State avg. commercial price13.30¢/kWh[8] Confirmed2026-07Shown
Generation within 50 km4.7 GW[9] derivedConfirmed202502Shown
Buildings (planned)18[1] derivedLikely2026-06-03Superseded / alternative
Buildings (planned)30[2] Confirmed2025-10-29Shown
Buildings (planned)30[2] AI-extractedLikely2025-10Superseded / alternative
Buildings operational16[1] estimatedLikely2026-06-03Superseded / alternative
Buildings operational0[1] estimatedLikely2024-02-09Superseded / alternative
Buildings operational0[1] estimatedLikely2024-06-10Superseded / alternative
Buildings operational0[1] estimatedLikely2025-05-10Superseded / alternative
Buildings operational7[1] estimatedLikely2025-06-23Superseded / alternative
Buildings operational7[1] estimatedLikely2025-09-26Superseded / alternative
Buildings operational7[1] estimatedLikely2025-10-17Superseded / alternative
Buildings operational11[1] estimatedLikely2025-12-23Superseded / alternative
Buildings operational11[1] estimatedLikely2026-02-09Superseded / alternative
Buildings operational16[1] estimatedLikely2026-03-23Superseded / alternative
Buildings operational7[2] Confirmed2025-10-29Shown
Buildings operational7[2] AI-extractedLikely2025-10Superseded / alternative
Building footprint1.47M sq ftway/1471517731 way/1471517732 way/1471517733 way/1471517734 way/1471517735 way/1[6] derivedLikely2026-09-27Shown
Site area1,200 acres[2] Confirmed2025-10-29Shown
Site area1,200 acres[2] AI-extractedLikely2025-10Superseded / alternative
Capital cost / investment$34.5B[1] estimatedLikely2026-06-03Superseded / alternative
Capital cost / investment$11B[2] Confirmed2025-10-29Shown
Capital cost / investment$11B[2] AI-extractedLikely2025-10Superseded / alternative
Compute (H100-equivalents)685,900[1] estimatedLikely2026-06-03Shown
Chip typesTrainium2[1] Confirmed2026-06-03Shown
Chip typesTrainium2[2] Confirmed2025-10-29Shown
Construction startFeb 9, 2024[1] derivedLikely2026-06-03Superseded / alternative
Construction startSep 2024[2] Confirmed2025-10-29Shown
First operationalJun 23, 2025[1] derivedLikely2026-06-03Superseded / alternative
First operationalOct 2025[2] AI-extractedLikely2025-10-29Shown
Expected completionMar 17, 2028[1] estimatedSpeculative2026-06-03Shown