Amazon IAD-195
Part of Amazon Web Services — Gainesville, VA campus
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Community map.
Grid path
- →facilityAmazon IAD-195
- →substationHeathcote Substation (230 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 1.51 km away. Proximity does not establish that it serves the site.
- →transmission230 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.5 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 38.80269, -77.62238
- Address
- County
- Prince William County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Operator
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Virginia statewide average, July 2026.
- State avg. commercial price
Virginia statewide average, July 2026.
- Generation within 50 km
24 EIA-reported plants within 50 km.
- Generation queued in county
16 active generation interconnection requests in Prince William County: Storage 1,350 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 1.5 km | 230 kV | [1] |
| Potomac Energy Center, LLC · Potomac Energy Center LLC | Power plant (Natural Gas) | 29.2 km | 766 MW | [6] |
| Remington · Virginia Electric & Power Co | Power plant (Natural Gas) | 31.5 km | 604 MW | [6] |
| Marsh Run Generation Facility · Old Dominion Electric Coop | Power plant (Natural Gas) | 33 km | 481 MW | [6] |
| Covanta Fairfax Energy · Covanta Fairfax Inc | Power plant (Biomass) | 35.2 km | 98 MW | [6] |
| Possum Point · Virginia Electric & Power Co | Power plant (Natural Gas) | 41.9 km | 645 MW | [6] |
| Covanta Alexandria/Arlington Energy · Covanta Alexandria/Arlington | Power plant (Biomass) | 42.8 km | 29 MW | [6] |
| Montgomery County Resource Recovery · Covanta Montgomery, Inc. | Power plant (Biomass) | 46.5 km | 54 MW | [6] |
| Dickerson Power · Dickerson Power, LLC | Power plant (Natural Gas) | 47.3 km | 299 MW | [6] |
| Heathcote Substation | Substation | 1.51 km | 230 kV | [1] |
| Haymarket Substation | Substation | 2.93 km | 230 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Gainesville-Loudoun 230 kVPJM AI2-231 | Storage | In study · proposed 2023-10 | 200 MW | [4] |
| Nokesville-Vint Hill 230 kVPJM AG2-113 | Storage | In study · proposed 2022-08 | 150 MW | [4] |
| Catharpin 230 kVPJM AG2-284 | Storage | In study · proposed 2023-12 | 150 MW | [4] |
| Liberty 230 kVPJM AG2-304 | Storage | In study · proposed 2023-12 | 150 MW | [4] |
| Possum Point 230 kVPJM AG2-306 | Storage | In study · proposed 2023-12 | 150 MW | [4] |
| Possum Point 230kVPJM AH2-034 | Storage | In study · proposed 2028-12 | 100 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredJan 22, 2025[7]
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 7397-36-1468 Prince William County, VA | — | 10.54 | — | — | [7] |
- Site area
Sum of county land area across parcels.
- Annual property tax
- Not yet sourced
Size
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Jan 22, 2025[7]
Deed recorded for parcel 7397-36-1468.
Other buildings on this campus
2- Amazon IAD-196Operating · 127,200 sq ft footprint
- Amazon IAD-197Operating · 130,400 sq ft footprint
All claims (provenance audit)
19| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Amazon IAD-195way/1280340214 name=Amazon IAD-195 | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-09-27 | Shown |
| Address | 14495 John Marshall Highway, Gainesville, VA 20155 | [1] | Likely | 2026-09-27 | Shown |
| Operator | Amazon Web Servicesoperator=Amazon Web Services | [1] | Likely | 2026-09-27 | Shown |
| Utility | Dominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Heathcote Substation (230 kV)way/834348787 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 1.5 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.35 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.68¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.08 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 129,400 sq ft | [1] derived | Likely | 2026-09-27 | Shown |
| Site area | 10.5 acres | [7] | Confirmed | 2026-09-27 | Shown |
| Parcel / land records | 7397-36-1468 (Prince William County) | [7] | Confirmed | 2026-09-27 | Shown |
| Land acquired | Jan 22, 2025 | [7] derived | Confirmed | 2026-09-27 | Shown |