AWS New Albany
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredFeb 13, 2025
Government record
- Feb 13, 2025 · Land acquisition / deed recorded[2]
- Feb 13, 2025 · Deed/transfer recorded for parcel 095-111648-00.000 (no sale price disclosed).[2]
- Apr 9, 2025 · Deed/transfer recorded for parcel 095-111756-00.024 (no sale price disclosed).[2]
- Mar 9, 2026 · Deed/transfer recorded for parcel 095-111408-00.000 (no sale price disclosed).[2]
- Sep 27, 2026 · Owner of record in county parcel data[2]
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationDec 1, 2024
Satellite imagery
- Dec 1, 2024 · Buildings 5-9 (eastern campus) operational. [New Albany’s Dec. 2024 report](https://newalbanyohio.org/wp-content/uploads/2025/01/CD-2024-12.pdf) lists AWS partial occupancy for 5 b[1]
- Mar 12, 2026 · Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on sate[1]
- OperationalDec 1, 2024
Satellite imagery · Government record
- Dec 1, 2024 · Buildings 5-9 (eastern campus) operational. [New Albany’s Dec. 2024 report](https://newalbanyohio.org/wp-content/uploads/2025/01/CD-2024-12.pdf) lists AWS partial occupancy for 5 b[1]
- Mar 12, 2026 · Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on sate[1]
- Sep 27, 2026 · County land use: 342: Light Manufacturing - 21-30% Office[2]
- Sep 27, 2026 · County land use: 305: Research/Chemical Labs[2]
- Sep 27, 2026 · County land use: 300: Industrial Vacant Land[2]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilityAWS New Albany
- →substationSatellite imageryLikely4 substation outlines traced inside the campus on satellite imagery; OSM maps Horizon Substation 0.35 km away
- →transmissionConesville - Corridor 345kV transmission line[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.37 km away). Not confirmed as the supply path.
- →utilityAmerican Electric Power[3]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 40.10491, -82.74348
- Address
- County
- Licking County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- Owner
- Utility
Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Ohio Edison CO, Licking Rural Electric INC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Estimated annual consumption
255 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
8 EIA-reported plants within 50 km.
- Generation queued in county
14 active generation interconnection requests in Licking County: Solar 1,773 MW, Storage 750 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Conesville - Corridor 345kV transmission line · American Electric Power | Transmission line | 0.37 km | 345 kV | [6] |
| 138 kV line | Transmission line | 0.38 km | 138 kV | [6] |
| Jug Street - Corridor · American Electric Power | Transmission line | 0.45 km | 345 kV | [6] |
| Jug Street - Corridor 345kV transmission line · American Electric Power | Transmission line | 0.52 km | 345 kV | [6] |
| 345 kV line · American Electric Power | Transmission line | 1.05 km | 345 kV | [6] |
| Jug Street - Kirk 345kV transmission line · American Electric Power | Transmission line | 1.12 km | 345 kV | [6] |
| Denison Solar Array · AEP Onsite Partners, LLC | Power plant (Solar) | 19.5 km | 2 MW | [9] |
| Dodge Park Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 28.6 km | 2 MW | [9] |
| St-1/1a Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 28.9 km | 1 MW | [9] |
| 3100 Valleyview Drive · Madison Energy Investments LLC | Power plant (Solar) | 29.4 km | 1 MW | [9] |
| Renick Run Pumping Station 03-04 · City of Columbus - (OH) | Power plant (Petroleum) | 30.1 km | 2 MW | [9] |
| Ps St-8 Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 30.5 km | 2 MW | [9] |
| O'Shaughnessy Hydro · City of Columbus - (OH) | Power plant (Hydroelectric) | 33 km | 5 MW | [9] |
| Suburban Landfill Gas Recovery · WM Renewable Energy LLC | Power plant (Biomass) | 47.5 km | 6 MW | [9] |
| Horizon Substation · American Electric Power | Substation | 0.35 km | 138 kV | [6] |
| Badger Substation · American Electric Power | Substation | 0.8 km | 138 kV | [6] |
| Unnamed substation | Substation | 0.86 km | 138 kV | [6] |
| Jug Street Substation · AEP Ohio | Substation | 1.11 km | 345 kV | [6] |
| Smith's Mill Substation · Energy Cooperative | Substation | 1.16 km | 138 kV | [6] |
| Unnamed substation | Substation | 1.75 km | 138 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Centerburg 138 kVPJM AI2-088 | Solar | In study · proposed 2025-12 | 413 MW | [7] |
| Centerburg 138 kVPJM AG1-034 | Solar | In study · proposed 2023-10 | 363 MW | [7] |
| Centerburg 138 kVPJM AH1-036 | Storage | In study · proposed 2024-07 | 278 MW | [7] |
| Centerburg 138 kVPJM AG1-024 | Solar | In study · proposed 2023-10 | 235 MW | [7] |
| Flint GridPJM AF1-062 | Storage | IA signed · proposed 2026-11 | 200 MW | [7] |
| Jug Street 138 kVPJM AI2-226 | Storage | In study · proposed 2022-08 | 200 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredFeb 13, 2025[2]
- Permitting—
- Construction startJul 1, 2022[1]
- First operationalDec 1, 2024[1]
- Expected completionJul 1, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
- $17.5M[2]Market value · tax year current (2026) · parcel 095-111756-00.024
- $3.2M[2]Market value — land · tax year current (2026) · parcel 095-111756-00.024
- $14.3M[2]Market value — improvements · tax year current (2026) · parcel 095-111756-00.024
- $20.4M[2]Market value · tax year current (2026) · parcel 095-111648-00.000
- $20.4M[2]Market value — land · tax year current (2026) · parcel 095-111648-00.000
- $65.7M[2]Market value · tax year current (2026) · parcel 095-111408-00.000
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 095-111756-00.024 Licking County, OH | CIVF VII - OH1M01 LLC 1 BEACON ST STE 2800 , BOSTON, MA | 15.87 | 342: Light Manufacturing - 21-30% Office | — | [2] |
| 095-111648-00.000 Licking County, OH | AMAZON DATA SERVICES INC PO BOX 80416 , SEATTLE, WA | 67.68 | 305: Research/Chemical Labs | — | [2] |
| 095-111408-00.000 Licking County, OH | AMAZON DATA SERVICES INC PO BOX 80416 , SEATTLE, WA | 199.81 | 300: Industrial Vacant Land | — | [2] |
- Site area
Sum of county land area across parcels.
- Land use
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
- Amazon Web Services CMH50 · 1.3 km · parcel 095-111744-00.000$12.8M · Jul 23, 2015 [2]
- NAO 1/NAO 2 · 4.1 km · parcel 094-107100-00.001$36.4M · Aug 10, 2017 [2]
- LCO 1 · 4.8 km · parcel 094-106782-00.000$34.3M · May 23, 2019 [2]
Size
- Parcel / land records
- 095-111756-00.024 (Licking County),095-111648-00.000 (Licking County),095-111408-00.000 (Licking County)[2]Confirmed
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
- Assessed value (official)
Timeline
- Jul 1, 2022[1]
Land clearing begins for Buildings 5-9 (eastern campus).
Buildings 5-9 (eastern campus) operational. New Albany’s Dec. 2024 report lists AWS partial occupancy for 5 buildings at the eastern campus. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed. The full IT power is much higher than 113 MW.
Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, northern campus Buildings 1-3 appear in late construction, with all roofs complete but nearby generator/cooling equipment still being installed for buildings 2-3. Building 4 is still early in construction. Eastern campus Buildings 5-9 appear complete and operational as expected. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed.
Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.
Expected operational date for the remaining tracked buildings (11, and 1-4) across the three campuses. This estimate is based on the previous buildings taking roughly 1.5 years from steel framing to complete operational status. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances listed.
- Apr 9, 2025[2]
Deed/transfer recorded for parcel 095-111756-00.024 (no sale price disclosed).
- Feb 13, 2025[2]
Deed/transfer recorded for parcel 095-111648-00.000 (no sale price disclosed).
- Mar 9, 2026[2]
Deed/transfer recorded for parcel 095-111408-00.000 (no sale price disclosed).
Buildings on this campus
13- Amazon Web Services CMH50Operating · 161,900 sq ft footprint
- Amazon Web Services CMH53Operating · 154,200 sq ft footprint
- Amazon Web Services CMH56Operating · 154,900 sq ft footprint
- Amazon Web Services CMH59Operating · 161,300 sq ft footprint
- Amazon Web Services CMH62Operating · 136,500 sq ft footprint
- Amazon Web ServicesOperating · 214,600 sq ft footprint
- Amazon Web ServicesOperating · 214,500 sq ft footprint
- Amazon Web ServicesOperating · 14,200 sq ft footprint
- Amazon Web ServicesOperating · 213,800 sq ft footprint
- Amazon Web ServicesOperating · 125,800 sq ft footprint
- Amazon Web ServicesOperating · 213,400 sq ft footprint
- Amazon Web ServicesOperating · 72,500 sq ft footprint
- Amazon Web ServicesOperating · 211,700 sq ft footprint
All claims (provenance audit)
52| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | AWS New Albany | [1] | Likely | 2026-05-18 | Shown |
| Status | Under construction | [1] derived | Likely | 2022-07-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-12-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-12 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-18 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-18 | Shown |
| Address | 13360 Miller Rd NW | [1] | Likely | 2026-05-18 | Shown |
| Property owner of record | Civf Vii - Oh1m01 LLCParcel 095-111756-00.024: CIVF VII - OH1M01 LLC | [2] | Confirmed | 2026-09-27 | Shown |
| Property owner of record | Amazon Web ServicesParcel 095-111648-00.000: AMAZON DATA SERVICES INC | [2] | Confirmed | 2026-09-27 | Shown |
| Property owner of record | Amazon Web ServicesParcel 095-111408-00.000: AMAZON DATA SERVICES INC | [2] | Confirmed | 2026-09-27 | Shown |
| Owner | Amazon Web ServicesOwner: Amazon | [1] | Confirmed | 2026-05-18 | Shown |
| Utility | American Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO) | [3] derived | Unverified | 2022 | Shown |
| Current facility power | 255 MW | [1] estimated | Likely | 2026-05-18 | Shown |
| Current facility power | 136 MW | [1] estimated | Likely | 2024-12-01 | Superseded / alternative |
| Current facility power | 255 MW | [1] estimated | Likely | 2026-03-12 | Superseded / alternative |
| Current IT capacity | 213 MW | [1] estimated | Likely | 2026-05-18 | Shown |
| Current IT capacity | 113 MW | [1] estimated | Likely | 2024-12-01 | Superseded / alternative |
| Current IT capacity | 213 MW | [1] estimated | Likely | 2026-03-12 | Superseded / alternative |
| Planned capacity | 405 MW | [1] estimated | Likely | 2026-05-18 | Shown |
| Estimated annual consumption | 1,564 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [5] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Horizon Substation (138 kV)way/1428181256 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 2.52 GW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 21 MW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 14 | [1] derived | Likely | 2026-05-18 | Shown |
| Buildings operational | 9 | [1] estimated | Likely | 2026-05-18 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2022-07-01 | Superseded / alternative |
| Buildings operational | 5 | [1] estimated | Likely | 2024-12-01 | Superseded / alternative |
| Buildings operational | 9 | [1] estimated | Likely | 2026-03-12 | Superseded / alternative |
| Site area | 283.4 acres | [2] | Confirmed | 2026-09-27 | Shown |
| Capital cost / investment | $8.1B | [1] estimated | Likely | 2026-05-18 | Shown |
| Parcel / land records | 095-111756-00.024 (Licking County) | [2] | Confirmed | 2026-09-27 | Shown |
| Parcel / land records | 095-111648-00.000 (Licking County) | [2] | Confirmed | 2026-09-27 | Shown |
| Parcel / land records | 095-111408-00.000 (Licking County) | [2] | Confirmed | 2026-09-27 | Shown |
| Assessed value (official) | $103.7M | [2] | Confirmed | 2026 | Shown |
| Land use | 342: Light Manufacturing - 21-30% Office | [2] | Confirmed | 2026-09-27 | Shown |
| Land use | 305: Research/Chemical Labs | [2] | Confirmed | 2026-09-27 | Superseded / alternative |
| Land use | 300: Industrial Vacant Land | [2] | Confirmed | 2026-09-27 | Superseded / alternative |
| Compute (H100-equivalents) | 201,100 | [1] estimated | Likely | 2026-05-18 | Shown |
| Chip types | Trainium2 | [1] | Confirmed | 2026-05-18 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-05-18 | Shown |
| Chip types | H200 | [1] | Confirmed | 2026-05-18 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-05-18 | Shown |
| Land acquired | Feb 13, 2025 | [2] derived | Confirmed | 2026-09-27 | Shown |
| Construction start | Jul 1, 2022 | [1] derived | Likely | 2026-05-18 | Shown |
| First operational | Dec 1, 2024 | [1] derived | Likely | 2026-05-18 | Shown |
| Expected completion | Jul 1, 2027 | [1] estimated | Speculative | 2026-05-18 | Shown |