CoreWeave Denton TX
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionNov 1, 2024
Model estimate · Satellite imagery
- Nov 1, 2024 · Reported status: under construction[1]
- Nov 1, 2024 · Construction start[1]
- Nov 1, 2024 · Construction start - The [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/TABS/Search/Print/TABS2025005706) reports Core Scientific is converting existing [1]
- May 31, 2025 · Reported status: expanding[1]
- EnergizationMay 31, 2025
Satellite imagery
- May 31, 2025 · First 8 MW billable tranche dedicated to AI [starts running at the site](https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001628280-25-023161/q12025coresci[1]
- Dec 31, 2025 · Half the campus energized. 67 billable MW [are now dedicated](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1085/11265/presentation/Q4+FY[1]
- Feb 23, 2026 · Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buil[1]
- Jul 3, 2026 · Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the [Q2 2026 Earnings call](https://d1io3yog0oux5.cloudfr[1]
- OperationalMay 31, 2025
Satellite imagery
- May 31, 2025 · First 8 MW billable tranche dedicated to AI [starts running at the site](https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001628280-25-023161/q12025coresci[1]
- Dec 31, 2025 · Half the campus energized. 67 billable MW [are now dedicated](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1085/11265/presentation/Q4+FY[1]
- Feb 23, 2026 · Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buil[1]
- Jul 3, 2026 · Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the [Q2 2026 Earnings call](https://d1io3yog0oux5.cloudfr[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityCoreWeave Denton TX
- →substationOn-site substation[1]Satellite imageryLikely4 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityDenton County Elec Coop, INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- Denton Energy Center (Natural Gas, 226 MW) is 0 km away[7]EIA plant within 1.5 km; proximity does not establish that it supplies the facilityNatural gasCo-located226 MWUnverified
Location & imagery
Mapped outline- Coordinates
- 33.21488, -97.21005
- Address
- County
- Denton County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 7 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Tri-County Electric Coop, INC (Tx), City of Denton - (Tx), Wise Electric Coop INC, Cooke County Elec Coop Assn, Texas-New Mexico Power CO, Oncor Electric Delivery Company LLC.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-05-31); not necessarily full build-out.
- Estimated annual consumption
367 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
39 EIA-reported plants within 50 km.
- Generation queued in county
1 active generation interconnection requests in Denton County: Storage 201 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Denton Energy Center · City of Denton - (TX) | Power plant (Natural Gas) | 0 km | 226 MW | [7] |
| Noble Solar · BT Noble Solar, LLC | Power plant (Solar) | 5.8 km | 400 MW | [7] |
| Spencer · City of Garland - (TX) | Power plant (Natural Gas) | 9.9 km | 122 MW | [7] |
| Tx10 Hummingbird Storage · Key Capture Energy | Power plant (Batteries) | 15.7 km | 100 MW | [7] |
| Porter Solar, LLC (Tx) · Porter Solar, LLC | Power plant (Solar) | 18.3 km | 245 MW | [7] |
| Connolly Bess · BT Connolly Storage, LLC | Power plant (Batteries) | 19.4 km | 125 MW | [7] |
| Chisholm Grid Energy Storage System · Chisholm Grid, LLC | Power plant (Batteries) | 38.2 km | 100 MW | [7] |
| Wildcat Creek Wind Farm LLC · Wildcat Creek Wind Farm LLC | Power plant (Wind) | 38.8 km | 175 MW | [7] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Oakley BESSERCOT 28INR0454 · Oakley BESS LLC | Storage | In study · proposed 2028-09 | 201 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startNov 1, 2024[1]
- First operationalMay 31, 2025[1]
- Expected completionMay 31, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-05-31); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
Timeline
- Nov 1, 2024[1]
Construction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.
First 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter.
Half the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings.
Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.
Buildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an earnings call from this date.
Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.
Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
Building 8 projected operational. TDLR project TABS2026028247 schedules Building A's data-hall fit-out for completion by this date.
All claims (provenance audit)
47| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | CoreWeave Denton TX | [1] | Likely | 2026-09-01 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-11-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-05-31 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-12-31 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-02 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-07-03 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-09-01 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-09-01 | Shown |
| Address | 8171 Jim Christal Rd, Denton, TX 76207 | [1] | Likely | 2026-09-01 | Shown |
| Owner | CoreWeaveOwner: CoreWeave | [1] | Confirmed | 2026-09-01 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Likely | 2026-09-01 | Shown |
| Utility | Denton County Elec Coop, INCterritory 5078: DENTON COUNTY ELEC COOP, INC (COOPERATIVE, DENTON COUNTY ELEC CO | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 367 MW | [1] estimated | Likely | 2026-09-01 | Shown |
| Current facility power | 11 MW | [1] estimated | Likely | 2025-05-31 | Superseded / alternative |
| Current facility power | 94 MW | [1] estimated | Likely | 2025-12-31 | Superseded / alternative |
| Current facility power | 183 MW | [1] estimated | Likely | 2026-02-23 | Superseded / alternative |
| Current facility power | 183 MW | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Current facility power | 367 MW | [1] estimated | Likely | 2026-07-03 | Superseded / alternative |
| Current IT capacity | 262 MW | [1] estimated | Likely | 2026-09-01 | Shown |
| Current IT capacity | 8 MW | [1] estimated | Likely | 2025-05-31 | Superseded / alternative |
| Current IT capacity | 67 MW | [1] estimated | Likely | 2025-12-31 | Superseded / alternative |
| Current IT capacity | 131 MW | [1] estimated | Likely | 2026-02-23 | Superseded / alternative |
| Current IT capacity | 131 MW | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Current IT capacity | 262 MW | [1] estimated | Likely | 2026-07-03 | Superseded / alternative |
| Planned capacity | 395 MW | [1] estimated | Likely | 2026-09-01 | Shown |
| Estimated annual consumption | 2,250 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [4] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Generation queued in county | 201 MW | [5] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.63 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 8 | [1] derived | Likely | 2026-09-01 | Shown |
| Buildings operational | 7 | [1] estimated | Likely | 2026-09-01 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-11-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-05-31 | Superseded / alternative |
| Buildings operational | 3 | [1] estimated | Likely | 2025-12-31 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2026-02-23 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Buildings operational | 7 | [1] estimated | Likely | 2026-07-03 | Superseded / alternative |
| Capital cost / investment | $9.9B | [1] estimated | Likely | 2026-09-01 | Shown |
| Compute (H100-equivalents) | 252,700 | [1] estimated | Likely | 2026-09-01 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-09-01 | Shown |
| Construction start | Nov 1, 2024 | [1] derived | Likely | 2026-09-01 | Shown |
| First operational | May 31, 2025 | [1] derived | Likely | 2026-09-01 | Shown |
| Expected completion | May 31, 2027 | [1] estimated | Speculative | 2026-09-01 | Shown |