CoreWeave Denton TX

Operating + expandingAI campusCampusDenton, Denton County, Texas
80% profile completeness
47 claims from 11 sources
Current facility power
367 MW[1]
Likelyestimated
Planned capacity
395 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$9.9B[1]
Likelyestimated
First operational
May 31, 2025[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H1 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Denton County Elec Coop, INC · ERCOT
Substation: On-site substation

Power reality

Announced
395 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
28 MW[1]
Building 8 under construction (satellite-tracked phases)
Operational
367 MW[1]
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2027-05-31 (modeled/speculative)[1]
  • Required: 395 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionNov 1, 2024
    Model estimate · Satellite imagery
    • Nov 1, 2024 · Reported status: under construction[1]
    • Nov 1, 2024 · Construction start[1]
    • Nov 1, 2024 · Construction start - The [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/TABS/Search/Print/TABS2025005706) reports Core Scientific is converting existing [1]
    • May 31, 2025 · Reported status: expanding[1]
  3. EnergizationMay 31, 2025
    Satellite imagery
    • May 31, 2025 · First 8 MW billable tranche dedicated to AI [starts running at the site](https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001628280-25-023161/q12025coresci[1]
    • Dec 31, 2025 · Half the campus energized. 67 billable MW [are now dedicated](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1085/11265/presentation/Q4+FY[1]
    • Feb 23, 2026 · Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buil[1]
    • Jul 3, 2026 · Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the [Q2 2026 Earnings call](https://d1io3yog0oux5.cloudfr[1]
  4. OperationalMay 31, 2025
    Satellite imagery
    • May 31, 2025 · First 8 MW billable tranche dedicated to AI [starts running at the site](https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001628280-25-023161/q12025coresci[1]
    • Dec 31, 2025 · Half the campus energized. 67 billable MW [are now dedicated](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1085/11265/presentation/Q4+FY[1]
    • Feb 23, 2026 · Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buil[1]
    • Jul 3, 2026 · Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the [Q2 2026 Earnings call](https://d1io3yog0oux5.cloudfr[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    CoreWeave Denton TX
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    4 substation outlines traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Denton County Elec Coop, INC[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    ERCOT[4]
    Service territoryLikely
    Balancing authority: ERCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

  • Denton Energy Center (Natural Gas, 226 MW) is 0 km away[7]
    EIA plant within 1.5 km; proximity does not establish that it supplies the facility
    Natural gasCo-located226 MWUnverified

Location & imagery

Mapped outline
Coordinates
33.21488, -97.21005
Address
8171 Jim Christal Rd, Denton, TX 76207[1]Likely
County
Denton County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    OpenAI[1]Likely
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
CoreWeave[1]Confirmed
End user
OpenAI[1]Likely
Utility

Most likely retail provider among 7 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Tri-County Electric Coop, INC (Tx), City of Denton - (Tx), Wise Electric Coop INC, Cooke County Elec Coop Assn, Texas-New Mexico Power CO, Oncor Electric Delivery Company LLC.

Power (all fields)

Current facility power
367 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
262 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
395 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-05-31); not necessarily full build-out.

Estimated annual consumption
2,250 GWh/yr[3]Speculativeestimated

367 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
ERCOT[4]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
ERCO[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
7.07¢/kWh[6]Confirmed

Texas statewide average, July 2026.

State avg. commercial price
8.47¢/kWh[6]Confirmed

Texas statewide average, July 2026.

Generation within 50 km
1.63 GW[7]Confirmedderived

39 EIA-reported plants within 50 km.

Generation queued in county
201 MW[5]Confirmedderived

1 active generation interconnection requests in Denton County: Storage 201 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Denton Energy Center · City of Denton - (TX)Power plant (Natural Gas)0 km226 MW[7]
Noble Solar · BT Noble Solar, LLCPower plant (Solar)5.8 km400 MW[7]
Spencer · City of Garland - (TX)Power plant (Natural Gas)9.9 km122 MW[7]
Tx10 Hummingbird Storage · Key Capture EnergyPower plant (Batteries)15.7 km100 MW[7]
Porter Solar, LLC (Tx) · Porter Solar, LLCPower plant (Solar)18.3 km245 MW[7]
Connolly Bess · BT Connolly Storage, LLCPower plant (Batteries)19.4 km125 MW[7]
Chisholm Grid Energy Storage System · Chisholm Grid, LLCPower plant (Batteries)38.2 km100 MW[7]
Wildcat Creek Wind Farm LLC · Wildcat Creek Wind Farm LLCPower plant (Wind)38.8 km175 MW[7]
Largest queued generation in this countyFuelQueue statusMWSource
Oakley BESSERCOT 28INR0454 · Oakley BESS LLCStorageIn study · proposed 2028-09201 MW[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Nov 1, 2024[1]
  5. First operational
    May 31, 2025[1]
  6. Expected completion
    May 31, 2027[1]
    Projected
Planned capacity
395 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-05-31); not necessarily full build-out.

Buildings (planned)
8[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
7[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational11 MWMay 31, 2025[1]
Buildings 2–3operational83 MWDec 31, 2025[1]
Building 4operational89 MWFeb 23, 2026[1]
Buildings 5–7operational184 MWJul 3, 2026[1]
Building 8under construction28 MWMay 31, 2027 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$9.9B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B200[1]Confirmed
Compute (H100-equivalents)
252,700[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    8 MWMay 31, 2025[1]→67 MWDec 31, 2025[1]→131 MWFeb 23, 2026[1]→262 MWJul 3, 2026[1]
  • Current facility power
    11 MWMay 31, 2025[1]→94 MWDec 31, 2025[1]→183 MWFeb 23, 2026[1]→367 MWJul 3, 2026[1]
  • Buildings operational
    0Nov 1, 2024[1]→1May 31, 2025[1]→3Dec 31, 2025[1]→4Feb 23, 2026[1]→7Jul 3, 2026[1]
  • Status
    Under constructionNov 1, 2024[1]→Operating + expandingMay 31, 2025[1]

Timeline

Construction start: Nov 1, 2024[1]
First operational: May 31, 2025[1]
  1. Nov 1, 2024[1]

    Construction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.

  2. May 31, 202511 MW facility power· 1 buildings operational[1]

    First 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter.

  3. Dec 31, 202594 MW facility power· 3 buildings operational[1]

    Half the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings.

  4. Feb 23, 2026183 MW facility power· 4 buildings operational[1]

    Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.

  5. Mar 2, 2026183 MW facility power· 4 buildings operational[1]

    Buildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an earnings call from this date.

  6. Jul 3, 2026367 MW facility power· 7 buildings operational[1]

    Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.

  7. Sep 1, 2026367 MW facility power· 7 buildings operational[1]

    Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.

  8. May 31, 2027Projected395 MW facility power· 8 buildings operational[1]

    Building 8 projected operational. TDLR project TABS2026028247 schedules Building A's data-hall fit-out for completion by this date.

All claims (provenance audit)

47
FieldValueSourceConfidenceAs ofStatus
NameCoreWeave Denton TX[1] Likely2026-09-01Shown
StatusUnder construction[1] derivedLikely2024-11-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-05-31Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-12-31Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-02-23Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-03-02Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-07-03Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-09-01Shown
Facility typeAI campus[1] derivedLikely2026-09-01Shown
Address8171 Jim Christal Rd, Denton, TX 76207[1] Likely2026-09-01Shown
OwnerCoreWeaveOwner: CoreWeave[1] Confirmed2026-09-01Shown
End usersOpenAIUsers: OpenAI[1] Likely2026-09-01Shown
UtilityDenton County Elec Coop, INCterritory 5078: DENTON COUNTY ELEC COOP, INC (COOPERATIVE, DENTON COUNTY ELEC CO[2] derivedUnverified2022Shown
Current facility power367 MW[1] estimatedLikely2026-09-01Shown
Current facility power11 MW[1] estimatedLikely2025-05-31Superseded / alternative
Current facility power94 MW[1] estimatedLikely2025-12-31Superseded / alternative
Current facility power183 MW[1] estimatedLikely2026-02-23Superseded / alternative
Current facility power183 MW[1] estimatedLikely2026-03-02Superseded / alternative
Current facility power367 MW[1] estimatedLikely2026-07-03Superseded / alternative
Current IT capacity262 MW[1] estimatedLikely2026-09-01Shown
Current IT capacity8 MW[1] estimatedLikely2025-05-31Superseded / alternative
Current IT capacity67 MW[1] estimatedLikely2025-12-31Superseded / alternative
Current IT capacity131 MW[1] estimatedLikely2026-02-23Superseded / alternative
Current IT capacity131 MW[1] estimatedLikely2026-03-02Superseded / alternative
Current IT capacity262 MW[1] estimatedLikely2026-07-03Superseded / alternative
Planned capacity395 MW[1] estimatedLikely2026-09-01Shown
Estimated annual consumption2,250 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTOERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.[4] derivedLikely—Shown
Balancing authorityERCO[2] derivedLikely—Shown
Generation queued in county201 MW[5] derivedConfirmed2026-09-01Shown
State avg. industrial price7.07¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price8.47¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km1.63 GW[7] derivedConfirmed202502Shown
Buildings (planned)8[1] derivedLikely2026-09-01Shown
Buildings operational7[1] estimatedLikely2026-09-01Shown
Buildings operational0[1] estimatedLikely2024-11-01Superseded / alternative
Buildings operational1[1] estimatedLikely2025-05-31Superseded / alternative
Buildings operational3[1] estimatedLikely2025-12-31Superseded / alternative
Buildings operational4[1] estimatedLikely2026-02-23Superseded / alternative
Buildings operational4[1] estimatedLikely2026-03-02Superseded / alternative
Buildings operational7[1] estimatedLikely2026-07-03Superseded / alternative
Capital cost / investment$9.9B[1] estimatedLikely2026-09-01Shown
Compute (H100-equivalents)252,700[1] estimatedLikely2026-09-01Shown
Chip typesB200[1] Confirmed2026-09-01Shown
Construction startNov 1, 2024[1] derivedLikely2026-09-01Shown
First operationalMay 31, 2025[1] derivedLikely2026-09-01Shown
Expected completionMay 31, 2027[1] estimatedSpeculative2026-09-01Shown