POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityGoogle
- →substationSouthland Substation (345 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.82 km away. Proximity does not establish that it serves the site.
- →transmission345 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.49 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.17539, -95.80690
- County
- Pottawattamie County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside overlapping MISO and SPP footprints; chosen by the balancing areas of the overlapping utilities.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Iowa statewide average, July 2026.
- State avg. commercial price
Iowa statewide average, July 2026.
- Generation within 50 km
11 EIA-reported plants within 50 km.
- Generation queued in county
1 active generation interconnection requests in Pottawattamie County: Wind 200 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 345 kV line · MidAmerican Energy | Transmission line | 0.49 km | 345 kV | [1] |
| 69 kV line · MidAmerican Energy | Transmission line | 0.52 km | 69 kV | [1] |
| 161 kV line · MidAmerican Energy | Transmission line | 1.21 km | 161 kV | [1] |
| Walter Scott Jr Energy Center · MidAmerican Energy Co | Power plant (Coal) | 2.9 km | 1.51 GW | [6] |
| Jones Street · Omaha Public Power District | Power plant (Petroleum) | 12.9 km | 124 MW | [6] |
| Sarpy County · Omaha Public Power District | Power plant (Natural Gas) | 13.7 km | 316 MW | [6] |
| North Omaha · Omaha Public Power District | Power plant (Coal) | 20.6 km | 564 MW | [6] |
| Cass County · Omaha Public Power District | Power plant (Natural Gas) | 28.5 km | 324 MW | [6] |
| Fort Calhoun Community Solar · DG Southwest Solar Portfolio 2019, LLC | Power plant (Solar) | 35.4 km | 5 MW | [6] |
| Elk City Station · Omaha Public Power District | Power plant (Biomass) | 44 km | 6 MW | [6] |
| Platteview Solar LLC · AES Distributed Energy | Power plant (Solar) | 47.9 km | 81 MW | [6] |
| Southland Substation · MidAmerican Energy | Substation | 0.82 km | 345 kV | [1] |
| MidAmerican Energy substation · MidAmerican Energy | Substation | 0.85 km | 345 kV | [1] |
| Unnamed substation | Substation | 1.2 km | 345 kV | [1] |
| Unnamed substation | Substation | 1.38 km | 345 kV | [1] |
| Unnamed substation | Substation | 1.48 km | 345 kV | [1] |
| River Bend Substation · MidAmerican Energy | Substation | 2.08 km | 161 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J2990 at Overland - J1859 POI 345kV Line TapMISO J2990 | Wind | In study · proposed 2025-06 | 200 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
16- Google Council Bluffs (East)Operating
- GoogleOperating · 76,100 sq ft footprint
- GoogleOperating · 319,200 sq ft footprint
- GoogleOperating · 258,500 sq ft footprint
- GoogleOperating · 211,700 sq ft footprint
- GoogleOperating · 129,900 sq ft footprint
- GoogleOperating · 132,200 sq ft footprint
- GoogleOperating · 132,400 sq ft footprint
- GoogleOperating · 130,900 sq ft footprint
- GoogleOperating · 129,700 sq ft footprint
- GoogleOperating · 134,600 sq ft footprint
- GoogleOperating · 174,400 sq ft footprint
- GoogleOperating · 174,700 sq ft footprint
- GoogleOperating · 158,400 sq ft footprint
- GoogleOperating · 295,000 sq ft footprint
- GoogleOperating · 297,100 sq ft footprint
All claims (provenance audit)
15| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Googleway/1073720212 name=Google | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-09-27 | Shown |
| Operator | Googleoperator=Google | [1] | Likely | 2026-09-27 | Shown |
| Utility | MidAmerican Energyterritory 12341: MIDAMERICAN ENERGY CO (INVESTOR OWNED, BERKSHIRE HATHAWAY ENERG | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | SOUTHWEST POWER P | [3] derived | Likely | — | Shown |
| Balancing authority | MISO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Southland Substation (345 kV)way/545122717 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.8 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 200 MW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.99¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.27¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.94 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 131,600 sq ft | [1] derived | Likely | 2026-09-27 | Shown |