Google Mesa
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredOct 28, 2025
Government record
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationJul 1, 2025
Satellite imagery
- Jul 1, 2025 · Building 1 is operational. This is based on the state of construction on 2025-03-02 as seen on [Google Earth](https://earth.google.com/web/@33.35450568,-111.67805903,407.02398359a,[1]
- Aug 15, 2026 · Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.[1]
- OperationalJul 1, 2025
Satellite imagery · Government record
- Jul 1, 2025 · Building 1 is operational. This is based on the state of construction on 2025-03-02 as seen on [Google Earth](https://earth.google.com/web/@33.35450568,-111.67805903,407.02398359a,[1]
- Aug 15, 2026 · Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.[1]
- Sep 27, 2026 · County land use: Property use code 2830[2]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Mesa
- →substationSatellite imageryLikely3 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.41 km away
- →transmissionKyrene - Browning 500KV[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.49 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 33.35343, -111.67610
- County
- Maricopa County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- Utility
Most likely retail provider among 12 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wapa-- Western Area Power Administration, Electrical Dist No8 Maricopa, City of Mesa - (Az), Usbia-San Carlos Project, Gila River Indian Utility Authority (Gricua), Maricopa County M W C Dist #1, ….
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
237 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Arizona statewide average, July 2026.
- State avg. commercial price
Arizona statewide average, July 2026.
- Generation within 50 km
29 EIA-reported plants within 50 km.
- Generation queued in county
5 active generation interconnection requests in Maricopa County: Solar + storage 1,100 MW, Solar 20 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 0.34 km | 230 kV | [6] |
| Kyrene - Browning 500KV · Arizona Public Service | Transmission line | 0.49 km | 500 kV | [6] |
| 69 kV line | Transmission line | 0.81 km | 69 kV | [6] |
| Santan · Salt River Project | Power plant (Natural Gas) | 7.3 km | 1.29 GW | [9] |
| Superstition Energy Storage · Superstition Energy Storage, LLC | Power plant (Batteries) | 14.4 km | 90 MW | [9] |
| Ocotillo · Arizona Public Service Co | Power plant (Natural Gas) | 23.2 km | 605 MW | [9] |
| Kyrene · Salt River Project | Power plant (Natural Gas) | 24.1 km | 525 MW | [9] |
| Copper Crossing Energy and Research Cent · Salt River Project | Power plant (Natural Gas) | 28.4 km | 88 MW | [9] |
| Horse Mesa · Salt River Project | Power plant (Pumped Storage) | 40.6 km | 151 MW | [9] |
| West Phoenix · Arizona Public Service Co | Power plant (Natural Gas) | 45.8 km | 909 MW | [9] |
| Sundance · Arizona Public Service Co | Power plant (Natural Gas) | 47.9 km | 410 MW | [9] |
| Unnamed substation | Substation | 0.41 km | 230 kV | [6] |
| Baseline Substation · Salt River Project | Substation | 1.96 km | 69 kV | [6] |
| Unnamed substation | Substation | 2.76 km | 69 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| HARQUAHALA FLATS 2CAISO 2027 | Solar + storage | In study · proposed 2028-04 | 400 MW | [7] |
| HARQUAHALA SUNRISECAISO 1678 | Solar + storage | In study · proposed 2030-04 | 300 MW | [7] |
| VULCANCAISO 1534 | Solar + storage | In study · proposed 2027-12 | 250 MW | [7] |
| HARQUAHALA SUNRISE 2CAISO 2029 | Solar + storage | In study · proposed 2026-09 | 150 MW | [7] |
| AGUA CALIENTE SOLAR 2CAISO 1222 | Solar | In study · proposed 2016-12 | 20 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
- $92.1M[2]Full cash value · tax year 2027 · parcel 304-05-019Q
- $51.6M[2]Limited property value (taxable basis) · tax year 2027 · parcel 304-05-019Q
- $87.7M[2]Full cash value · tax year 2027 · parcel 304-05-019P
- $49.1M[2]Limited property value (taxable basis) · tax year 2027 · parcel 304-05-019P
- $76.1M[2]Full cash value · tax year 2026 · parcel 304-05-019Q
- $88.5M[2]Full cash value · tax year 2026 · parcel 304-05-019P
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 304-05-019Q Maricopa County, AZ | STONE APPLICATIONS LLC 1600 AMPHITHEATRE PKWY MOUNTAIN VIEW CA USA 94043 | 70.91 | CONTACT LOCAL JURISDICTION · Property use code 2830 | — | [2] |
| 304-05-019P Maricopa County, AZ | STONE APPLICATIONS LLC 1600 AMPHITHEATRE PKWY MOUNTAIN VIEW CA USA 94043 | 114.07 | CONTACT LOCAL JURISDICTION · Property use code 2830 | — | [2] |
- Site area
Sum of county land area across parcels.
- Land use
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
- EdgeConneX PHX02 Data Center · 2.7 km · parcel 304-03-982$187M · Aug 1, 2022 [2]
- Comarch · 3.8 km · parcel 304-04-918A$1.2M · Apr 1, 2020 [2]
- Alliance Technology · 5.7 km · parcel 140-69-027$499,000 · May 1, 2022 [2]
- The Chatfield Group · 7.7 km · parcel 140-66-892$1M · May 1, 2019 [2]
- All About Serving Process Server · 13.0 km · parcel 302-84-928$2.6M · Oct 1, 2021 [2]
- Myndshift Technologies · 14.1 km · parcel 141-37-056D$1.9M · Feb 1, 2020 [2]
Size
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
- Assessed value (official)
Timeline
- Jul 1, 2023[1]
Land clearing begins for the entire site.
Building 1 is operational. This is based on the state of construction on 2025-03-02 as seen on Google Earth, where building shell and external components seems to have been completed, but there is still a lot of construction equipment present. That equipment appears to have been cleared up by this date, 4 months later, with the 2025-09-07 satellite imagery providing an upper bound. Construction has begun on the Building 2 roof, with work beginning on the areas for cooling and generators as well.
Building 2 roof is mostly completed. Building 2's backup generators are almost complete, and cooling is a little more than halfway complete. The Building 2 substation is also under construction.
Building 2 is close to being operational. There is only construction left on the backup generators, which are almost complete. Some equipment is also strewn around the building, especially near the air-cooled chillers. Preparation seems to have begun for Building 3 at the site.
Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.
- Oct 28, 2025[2]
Deed recorded for parcel 304-05-019Q (owner of record: Stone Applications LLC).
- Oct 28, 2025[2]
Deed recorded for parcel 304-05-019P (owner of record: Stone Applications LLC).
All claims (provenance audit)
49| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Mesa | [1] | Likely | 2026-08-15 | Shown |
| Status | Under construction | [1] derived | Likely | 2023-07-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-07-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-09-07 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-15 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-08-15 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-08-15 | Shown |
| Property owner of record | Stone Applications LLCParcel 304-05-019Q: STONE APPLICATIONS LLC | [2] | Confirmed | 2026-09-27 | Shown |
| Property owner of record | Stone Applications LLCParcel 304-05-019P: STONE APPLICATIONS LLC | [2] | Confirmed | 2026-09-27 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-08-15 | Shown |
| Utility | Salt River Projectterritory 16572: SALT RIVER PROJECT (POLITICAL SUBDIVISION, SALT RIVER PROJECT) | [3] derived | Unverified | 2022 | Shown |
| Current facility power | 237 MW | [1] estimated | Likely | 2026-08-15 | Shown |
| Current facility power | 126 MW | [1] estimated | Likely | 2025-07-01 | Superseded / alternative |
| Current facility power | 126 MW | [1] estimated | Likely | 2025-09-07 | Superseded / alternative |
| Current facility power | 126 MW | [1] estimated | Likely | 2026-05-15 | Superseded / alternative |
| Current IT capacity | 183 MW | [1] estimated | Likely | 2026-08-15 | Shown |
| Current IT capacity | 90 MW | [1] estimated | Likely | 2025-07-01 | Superseded / alternative |
| Current IT capacity | 90 MW | [1] estimated | Likely | 2025-09-07 | Superseded / alternative |
| Current IT capacity | 90 MW | [1] estimated | Likely | 2026-05-15 | Superseded / alternative |
| Estimated annual consumption | 1,453 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [5] derived | Likely | — | Shown |
| Balancing authority | SRP | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (230 kV)way/1292956193 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 500 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.12 GW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.35¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.12¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.33 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-08-15 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-08-15 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2023-07-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-07-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-09-07 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-05-15 | Superseded / alternative |
| Building footprint | 287,400 sq ftway/1372772726 | [6] derived | Likely | 2026-09-27 | Shown |
| Site area | 185 acres | [2] | Confirmed | 2026-09-27 | Shown |
| Capital cost / investment | $6.9B | [1] estimated | Likely | 2026-08-15 | Shown |
| Parcel / land records | 304-05-019Q (Maricopa County) | [2] | Confirmed | 2026-09-27 | Shown |
| Parcel / land records | 304-05-019P (Maricopa County) | [2] | Confirmed | 2026-09-27 | Shown |
| Assessed value (official) | $179.8M | [2] | Confirmed | 2027 | Shown |
| Land use | Property use code 2830 | [2] | Confirmed | 2026-09-27 | Shown |
| Land use | Property use code 2830 | [2] | Confirmed | 2026-09-27 | Superseded / alternative |
| Compute (H100-equivalents) | 289,500 | [1] estimated | Likely | 2026-08-15 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-08-15 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-08-15 | Shown |
| Land acquired | Oct 28, 2025 | [2] derived | Confirmed | 2026-09-27 | Shown |
| Construction start | Jul 1, 2023 | [1] derived | Likely | 2026-08-15 | Shown |
| First operational | Jul 1, 2025 | [1] derived | Likely | 2026-08-15 | Shown |