Google The Dalles
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle The Dalles
- →substationSatellite imageryLikely3 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.22 km away
- →transmission230 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.24 km away). Not confirmed as the supply path.
- →utilityNorthern Wasco County Pud[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 45.62406, -121.20767
- Address
- County
- Wasco County
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Bonneville Power Administration.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
185 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Oregon statewide average, July 2026.
- State avg. commercial price
Oregon statewide average, July 2026.
- Generation within 50 km
15 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 0.24 km | 230 kV | [5] |
| The Dalles-Discovery No 1 · Bonneville Power Administration | Transmission line | 0.41 km | 115 kV | [5] |
| Discovery-Chenoweth No 1 · Bonneville Power Administration | Transmission line | 0.95 km | 115 kV | [5] |
| 115 kV line | Transmission line | 1.2 km | 115 kV | [5] |
| Big Eddy-Quenett Creek No 1 · Bonneville Power Administration | Transmission line | 1.33 km | 230 kV | [5] |
| Big Eddy-Quenett Creek No 2 · Bonneville Power Administration | Transmission line | 1.35 km | 230 kV | [5] |
| The Dalles · USACE Northwestern Division | Power plant (Hydroelectric) | 5.8 km | 1.82 GW | [7] |
| Windy Flats Wind Project · Windy Flats Partners LLC | Power plant (Wind) | 31.2 km | 262 MW | [7] |
| Goldendale Generating Station · Puget Sound Energy Inc | Power plant (Natural Gas) | 35.8 km | 264 MW | [7] |
| Golden Hill Wind · Avangrid Power LLC | Power plant (Wind) | 39.4 km | 201 MW | [7] |
| John Day · USACE Northwestern Division | Power plant (Hydroelectric) | 41.2 km | 2.05 GW | [7] |
| Tuolumne Wind Project · Turlock Irrigation District | Power plant (Wind) | 42.1 km | 136 MW | [7] |
| Biglow Canyon Wind Farm · Portland General Electric Co | Power plant (Wind) | 47.1 km | 450 MW | [7] |
| Klondike Windpower II · Avangrid Power LLC | Power plant (Wind) | 48.2 km | 81 MW | [7] |
| Unnamed substation | Substation | 0.22 km | 230 kV | [5] |
| Unnamed substation | Substation | 0.28 km | 230 kV | [5] |
| Unnamed substation | Substation | 0.34 km | 230 kV | [5] |
| Bonneville Power Administration substation · Bonneville Power Administration | Substation | 0.96 km | 115 kV | [5] |
| Unnamed substation | Substation | 1.2 km | — | [5] |
| Unnamed substation | Substation | 1.23 km | 115 kV | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- May 21, 2023[1]
First signs of construction.
Building 1 is estimated to be operational, based on all external equipment being installed.
Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building.
Buildings on this campus
3- Google Data Center The Dalles OregonOperating
- GoogleOperating · 287,800 sq ft footprint
- GoogleOperating · 287,700 sq ft footprint
All claims (provenance audit)
33| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google The Dalles | [1] | Likely | 2026-04-29 | Shown |
| Status | Under construction | [1] derived | Likely | 2023-05-21 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-03-07 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-04-29 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-04-29 | Shown |
| Address | 3500 River Rd, The Dalles, OR | [1] | Likely | 2026-04-29 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-04-29 | Shown |
| Utility | Northern Wasco County Pudterritory 13788: NORTHERN WASCO COUNTY PUD (POLITICAL SUBDIVISION, NORTHERN WASC | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 185 MW | [1] estimated | Likely | 2026-04-29 | Shown |
| Current facility power | 93 MW | [1] estimated | Likely | 2025-03-07 | Superseded / alternative |
| Current IT capacity | 154 MW | [1] estimated | Likely | 2026-04-29 | Shown |
| Current IT capacity | 77 MW | [1] estimated | Likely | 2025-03-07 | Superseded / alternative |
| Estimated annual consumption | 1,134 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | BPAT | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (230 kV)way/1525007546 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 8.92¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.60¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.35 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-04-29 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-04-29 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2023-05-21 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-03-07 | Superseded / alternative |
| Capital cost / investment | $5.8B | [1] estimated | Likely | 2026-04-29 | Shown |
| Compute (H100-equivalents) | 175,300 | [1] estimated | Likely | 2026-04-29 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-04-29 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-04-29 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-04-29 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-04-29 | Shown |
| Construction start | May 21, 2023 | [1] derived | Likely | 2026-04-29 | Shown |
| First operational | Mar 7, 2025 | [1] derived | Likely | 2026-04-29 | Shown |