DC
/

Meta

OperatingHyperscaleBuildingUtah County, Utah

Part of Meta Eagle Mountain

20% profile completeness
14 claims from 5 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Building footprint
628,900 sq ft[1]
Likelyderived
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Operating (community-mapped, unverified)
Low confidence
Project verification
Unverified
Evidence is limited to community map.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
PacifiCorp · None (non-RTO region)
Substation: Unnamed substation (345 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalSep 27, 2026
    Community map
    • Sep 27, 2026 · Reported status: operating[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.

Grid path

  1. facility
    Meta
  2. substation
    Unnamed substation (345 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 0.87 km away. Proximity does not establish that it serves the site.
  3. transmission
    345 kV line[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.87 km away). Not confirmed as the supply path.
  4. utility
    PacifiCorp[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[3]
    Service territoryLikely
    Balancing authority: PACW, PACE
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
40.27241, -112.01447
County
Utah County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Meta[1]Likely
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Operator
Meta[1]Likely
Utility

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[3]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
PACW, PACE[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (345 kV)[1]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.9 km[1]Likelyderived
Highest-voltage line nearby
345 kV[1]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.10¢/kWh[4]Confirmed

Utah statewide average, July 2026.

State avg. commercial price
10.85¢/kWh[4]Confirmed

Utah statewide average, July 2026.

Generation within 50 km
1.76 GW[5]Confirmedderived

22 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
345 kV lineTransmission line0.87 km345 kV[1]
Lake Side Power Plant · PacifiCorpPower plant (Natural Gas)23 km1.18 GW[5]
Nebo Power Station · Utah Associated Mun Power SysPower plant (Natural Gas)33.7 km130 MW[5]
Whitehead · City of Springville - (UT)Power plant (Natural Gas)35 km24 MW[5]
Spanish Fork Wind Park 2 LLC · Spanish Fork Wind Park 2, LLCPower plant (Wind)43 km19 MW[5]
West Valley Generation Project · Utah Municipal Power AgencyPower plant (Natural Gas)43.9 km185 MW[5]
Murray Turbine · City of Murray - (UT)Power plant (Natural Gas)45.4 km36 MW[5]
Clover Creek Solar Community Solar · AES Distributed EnergyPower plant (Solar)49.2 km80 MW[5]
Kennecott Power Plant · Kennecott Utah CopperPower plant (Other)49.7 km38 MW[5]
Unnamed substationSubstation0.87 km345 kV[1]
PacifiCorp substation · PacifiCorpSubstation1.31 km345 kV[1]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
628,900 sq ft[1]Likelyderived

Computed from the mapped OSM building outline.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

Other buildings on this campus

5
  • Meta Eagle MountainOperating
  • MetaOperating · 345,200 sq ft footprint
  • MetaOperating · 627,100 sq ft footprint
  • MetaOperating · 379,200 sq ft footprint
  • MetaOperating · 310,500 sq ft footprint

All claims (provenance audit)

14
FieldValueSourceConfidenceAs ofStatus
NameMetaway/1035123473 name=Meta[1] Likely2026-09-27Shown
StatusOperating[1] derivedUnverified2026-09-27Shown
Facility typeHyperscale[1] derivedUnverified2026-09-27Shown
OperatorMetaoperator=Meta[1] Likely2026-09-27Shown
UtilityPacifiCorpterritory 14354: PACIFICORP (INVESTOR OWNED, PACIFICORP)[2] derivedLikely2022Shown
ISO / RTONone (non-RTO region)[3] derivedLikely—Shown
Balancing authorityPACW, PACE[2] derivedLikely—Shown
Nearest mapped substationUnnamed substation (345 kV)way/1473440687[1] derivedLikely2026-09-28Shown
Distance to substation0.9 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[1] derivedLikely2026-09-28Shown
State avg. industrial price9.10¢/kWh[4] Confirmed2026-07Shown
State avg. commercial price10.85¢/kWh[4] Confirmed2026-07Shown
Generation within 50 km1.76 GW[5] derivedConfirmed202502Shown
Building footprint628,900 sq ft[1] derivedLikely2026-09-27Shown