Microsoft Goodyear
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationApr 24, 2023
Satellite imagery
- Apr 24, 2023 · Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
- Jan 16, 2025 · Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
- Sep 1, 2025 · Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
- OperationalApr 24, 2023
Satellite imagery · Government record
- Apr 24, 2023 · Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
- Jan 16, 2025 · Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
- Sep 1, 2025 · Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
- Sep 27, 2026 · County land use: Property use code 1507[2]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilityMicrosoft Goodyear
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.4 km away
- →transmissionPalo Verde - Rudd 500KV[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.98 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 33.41089, -112.36483
- Address
- County
- Maricopa County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 11 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wapa-- Western Area Power Administration, Electrical Dist No8 Maricopa, Usbia-San Carlos Project, Gila River Indian Utility Authority (Gricua), Maricopa County M W C Dist #1, Buckeye Water C&D District, ….
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
263 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Arizona statewide average, July 2026.
- State avg. commercial price
Arizona statewide average, July 2026.
- Generation within 50 km
40 EIA-reported plants within 50 km.
- Generation queued in county
5 active generation interconnection requests in Maricopa County: Solar + storage 1,100 MW, Solar 20 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 0.37 km | 230 kV | [6] |
| 69 kV line | Transmission line | 0.37 km | 69 kV | [6] |
| Palo Verde - Rudd 500KV · Arizona Public Service | Transmission line | 0.98 km | 500 kV | [6] |
| 345 kV line | Transmission line | 1.11 km | 345 kV | [6] |
| Jojoba - Kyrene 500KV · Arizona Public Service | Transmission line | 1.16 km | 500 kV | [6] |
| West Phoenix · Arizona Public Service Co | Power plant (Natural Gas) | 19.5 km | 909 MW | [9] |
| Agua Fria · Salt River Project | Power plant (Natural Gas) | 21.3 km | 741 MW | [9] |
| Ocotillo · Arizona Public Service Co | Power plant (Natural Gas) | 42 km | 605 MW | [9] |
| Red Hawk · Arizona Public Service Co | Power plant (Natural Gas) | 45 km | 1 GW | [9] |
| Palo Verde · Arizona Public Service Co | Power plant (Nuclear) | 46.2 km | 3.94 GW | [9] |
| Mesquite Generating Station Block 2 · Mesquite Power LLC | Power plant (Natural Gas) | 46.9 km | 624 MW | [9] |
| Mesquite Generating Station Block 1 · Salt River Project | Power plant (Natural Gas) | 46.9 km | 620 MW | [9] |
| Arlington Valley Energy Facility · Arlington Valley LLC | Power plant (Natural Gas) | 49.3 km | 580 MW | [9] |
| Unnamed substation | Substation | 0.4 km | 230 kV | [6] |
| Unnamed substation | Substation | 0.52 km | 69 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| HARQUAHALA FLATS 2CAISO 2027 | Solar + storage | In study · proposed 2028-04 | 400 MW | [7] |
| HARQUAHALA SUNRISECAISO 1678 | Solar + storage | In study · proposed 2030-04 | 300 MW | [7] |
| VULCANCAISO 1534 | Solar + storage | In study · proposed 2027-12 | 250 MW | [7] |
| HARQUAHALA SUNRISE 2CAISO 2029 | Solar + storage | In study · proposed 2026-09 | 150 MW | [7] |
| AGUA CALIENTE SOLAR 2CAISO 1222 | Solar | In study · proposed 2016-12 | 20 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 500-07-984A Maricopa County, AZ | MICROSOFT CORPORATION 1 MICROSOFT WAY REDMOND WA USA 98052 | 189.11 | CONTACT LOCAL JURISDICTION · Property use code 1507 | — | [2] |
- Site area
Sum of county land area across parcels.
- Land use
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
- Cogent Data Center · 29.5 km · parcel 113-54-017A$8.3M · Jun 1, 2026 [2]
- 1GServers · 33.9 km · parcel 122-76-036$3.2M · Feb 1, 2025 [2]
- Alembic Computer Services, Inc. · 36.0 km · parcel 123-31-001E$35M · Jul 1, 2025 [2]
- Iron Mountain AZP-2 · 36.2 km · parcel 125-08-002C$8.6M · Sep 1, 2015 [2]
- Iron Mountain AZP-1 · 36.4 km · parcel 125-08-007A$106.9M · Jan 1, 2018 [2]
- J-Curve Technologies · 36.5 km · parcel 124-58-126$11.7M · Dec 1, 2025 [2]
Size
- Parcel / land records
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity
- Current facility power
- Buildings operational
- Status
Timeline
- Jun 21, 2021[1]
Land clearing begins for Building 1.
Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
Confirmation that Building 3 and 4 look complete.
Foundations appear to be underway for Building 5 and 6, just north of Building 4.
- Oct 30, 2024[2]
Deed recorded for parcel 500-07-984A (owner of record: Microsoft Corporation).
Buildings on this campus
5All claims (provenance audit)
52| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Microsoft Goodyear | [1] | Likely | 2026-04-27 | Shown |
| Status | Under construction | [1] derived | Likely | 2021-06-21 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2023-04-24 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-01-16 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-09-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-11-12 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-04-27 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-04-27 | Shown |
| Address | 14250 W Broadway Rd, Goodyear, AZ 85338 | [1] | Likely | 2026-04-27 | Shown |
| Property owner of record | MicrosoftParcel 500-07-984A: MICROSOFT CORPORATION | [2] | Confirmed | 2026-09-27 | Shown |
| Owner | MicrosoftOwner: Microsoft | [1] | Confirmed | 2026-04-27 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Likely | 2026-04-27 | Shown |
| End users | MicrosoftUsers: Microsoft | [1] | Confirmed | 2026-04-27 | Shown |
| Utility | Salt River Projectterritory 16572: SALT RIVER PROJECT (POLITICAL SUBDIVISION, SALT RIVER PROJECT) | [3] derived | Unverified | 2022 | Shown |
| Current facility power | 263 MW | [1] estimated | Likely | 2026-04-27 | Shown |
| Current facility power | 53 MW | [1] estimated | Likely | 2023-04-24 | Superseded / alternative |
| Current facility power | 105 MW | [1] estimated | Likely | 2025-01-16 | Superseded / alternative |
| Current facility power | 263 MW | [1] estimated | Likely | 2025-09-01 | Superseded / alternative |
| Current facility power | 263 MW | [1] estimated | Likely | 2025-11-12 | Superseded / alternative |
| Current IT capacity | 202 MW | [1] estimated | Likely | 2026-04-27 | Shown |
| Current IT capacity | 40 MW | [1] estimated | Likely | 2023-04-24 | Superseded / alternative |
| Current IT capacity | 81 MW | [1] estimated | Likely | 2025-01-16 | Superseded / alternative |
| Current IT capacity | 202 MW | [1] estimated | Likely | 2025-09-01 | Superseded / alternative |
| Current IT capacity | 202 MW | [1] estimated | Likely | 2025-11-12 | Superseded / alternative |
| Estimated annual consumption | 1,613 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [5] derived | Likely | — | Shown |
| Balancing authority | SRP | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (230 kV)way/1091128477 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 500 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.12 GW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.35¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.12¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 11.7 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 4 | [1] derived | Likely | 2026-04-27 | Shown |
| Buildings operational | 4 | [1] estimated | Likely | 2026-04-27 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2021-06-21 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2023-04-24 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-01-16 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2025-09-01 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2025-11-12 | Superseded / alternative |
| Site area | 189.1 acres | [2] | Confirmed | 2026-09-27 | Shown |
| Capital cost / investment | $7.7B | [1] estimated | Likely | 2026-04-27 | Shown |
| Parcel / land records | 500-07-984A (Maricopa County) | [2] | Confirmed | 2026-09-27 | Shown |
| Assessed value (official) | $357M | [2] | Confirmed | 2027 | Shown |
| Land use | Property use code 1507 | [2] | Confirmed | 2026-09-27 | Shown |
| Compute (H100-equivalents) | 205,200 | [1] estimated | Likely | 2026-04-27 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-04-27 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-04-27 | Shown |
| Land acquired | Oct 30, 2024 | [2] derived | Confirmed | 2026-09-27 | Shown |
| Construction start | Jun 21, 2021 | [1] derived | Likely | 2026-04-27 | Shown |
| First operational | Apr 24, 2023 | [1] derived | Likely | 2026-04-27 | Shown |