Microsoft SAT40
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionDec 28, 2018
Model estimate · Satellite imagery
- Dec 28, 2018 · Reported status: under construction[1]
- Dec 28, 2018 · Construction start[1]
- Dec 28, 2018 · Land clearing begins for the site, specifically digging up a parking lot and making outlines for the buildings. Evident on [Google Earth](https://earth.google.com/web/@29.4149522,-[1]
- May 24, 2024 · Reported status: expanding[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMicrosoft SAT40
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps Rafter Substation 0.15 km away
- →transmission138 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.1 km away). Not confirmed as the supply path.
- →utilityMedina Electric Coop, INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 29.41625, -98.80475
- Address
- County
- Bexar County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Karnes Electric Coop INC, Bandera Electric Coop, INC, AEP Texas Central Company.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
106 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
19 EIA-reported plants within 50 km.
- Generation queued in county
21 active generation interconnection requests in Bexar County: Storage 4,771 MW, Solar 152 MW, Gas 35 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.1 km | 138 kV | [5] |
| Leon Creek · City of San Antonio - (TX) | Power plant (Natural Gas) | 23.3 km | 184 MW | [8] |
| Oci Alamo Solar I Hybrid · OCI Energy LLC | Power plant (Solar) | 38.4 km | 41 MW | [8] |
| Blue Wing Solar Energy Generation · Duke Energy Renewables Services | Power plant (Solar) | 41.1 km | 14 MW | [8] |
| Arthur Von Rosenberg · City of San Antonio - (TX) | Power plant (Natural Gas) | 44.5 km | 518 MW | [8] |
| V H Braunig · City of San Antonio - (TX) | Power plant (Natural Gas) | 44.6 km | 1.05 GW | [8] |
| O W Sommers · City of San Antonio - (TX) | Power plant (Natural Gas) | 48.1 km | 830 MW | [8] |
| J K Spruce · City of San Antonio - (TX) | Power plant (Coal) | 48.4 km | 1.35 GW | [8] |
| Oci Alamo 4, LLC · Consolidated Edison Development Inc. | Power plant (Solar) | 49.5 km | 40 MW | [8] |
| Rafter Substation · CPS Energy | Substation | 0.15 km | 138 kV | [5] |
| CPS Energy substation · CPS Energy | Substation | 1.55 km | 138 kV | [5] |
| Texas Research Substation · CPS Energy | Substation | 1.71 km | 138 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Howard Road BESSERCOT 29INR0173 · Project Fast Flow LLC | Storage | In study · proposed 2028-04 | 618 MW | [6] |
| Orbit Energy StorageERCOT 27INR0082 · GCI Orbit Energy Storage, LLC | Storage | In study · proposed 2027-06 | 502 MW | [6] |
| Bernice Energy StorageERCOT 27INR0294 · Bernice Energy Storage LLC | Storage | In study · proposed 2029-02 | 403 MW | [6] |
| Mission Station Energy Storage IERCOT 28INR0474 · Mission Station LLC | Storage | In study · proposed 2030-05 | 375 MW | [6] |
| Mission Station Energy Storage IIERCOT 28INR0475 · Mission Station LLC | Storage | In study · proposed 2030-05 | 375 MW | [6] |
| Quela BESSERCOT 22INR0423 · BRP Quela BESS LLC | Storage | In study · proposed 2027-12 | 301 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Dec 28, 2018[1]
Land clearing begins for the site, specifically digging up a parking lot and making outlines for the buildings. Evident on Google Earth.
Building 1 operational. Estimated 3 months out from February, when there was still construction equipment.
Building 2 operational. No more construction on building, and surrounding roads are also complete.
Site has already been completed, with no more visible construction on any building.
Buildings on this campus
7- Microsoft Texas Research Park CampusOperating
- Microsoft TRP2Operating · 170,400 sq ft footprint
- Microsoft TRP1Operating · 178,100 sq ft footprint
- Microsoft TRP3 (SAT46)Operating · 229,700 sq ft footprint
- MicrosoftOperating · 229,700 sq ft footprint
- MicrosoftOperating · 229,700 sq ft footprint
- MicrosoftOperating · 152,100 sq ft footprint
All claims (provenance audit)
36| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Microsoft SAT40 | [1] | Likely | 2026-02-04 | Shown |
| Status | Under construction | [1] derived | Likely | 2018-12-28 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-05-24 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-12-01 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-02-04 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-02-04 | Shown |
| Address | 15000 Lambda Drive, San Antonio, TX 78245 | [1] | Likely | 2026-02-04 | Shown |
| Owner | MicrosoftOwner: Microsoft | [1] | Confirmed | 2026-02-04 | Shown |
| Utility | Medina Electric Coop, INCterritory 12268: MEDINA ELECTRIC COOP, INC (COOPERATIVE, MEDINA ELECTRIC COOP, I | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 106 MW | [1] estimated | Likely | 2026-02-04 | Shown |
| Current facility power | 66 MW | [1] estimated | Likely | 2024-05-24 | Superseded / alternative |
| Current facility power | 106 MW | [1] estimated | Likely | 2025-12-01 | Superseded / alternative |
| Current IT capacity | 75 MW | [1] estimated | Likely | 2026-02-04 | Shown |
| Current IT capacity | 47 MW | [1] estimated | Likely | 2024-05-24 | Superseded / alternative |
| Current IT capacity | 75 MW | [1] estimated | Likely | 2025-12-01 | Superseded / alternative |
| Estimated annual consumption | 650 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [4] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Rafter Substation (138 kV)way/639176169 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 4.96 GW | [6] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.1 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-02-04 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-02-04 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2018-12-28 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-05-24 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-12-01 | Superseded / alternative |
| Capital cost / investment | $2.8B | [1] estimated | Likely | 2026-02-04 | Shown |
| Compute (H100-equivalents) | 64,700 | [1] estimated | Likely | 2026-02-04 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-02-04 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-02-04 | Shown |
| Construction start | Dec 28, 2018 | [1] derived | Likely | 2026-02-04 | Shown |
| First operational | May 24, 2024 | [1] derived | Likely | 2026-02-04 | Shown |