OpenAI Stargate Michigan

Under constructionAI campusCampusWashtenaw County, Michigan
70% profile completeness
39 claims from 14 sources
Current facility power
Not yet sourced
Planned capacity
1.4 GW[3][5]
LikelyDisputed
Floor area
1.65M sq ft[2]
Likely
Buildings (planned)
LikelyderivedDisputed
Capital cost / investment
$7B[5]
Likely
First operational
Dec 31, 2028[1]
Speculativeestimated

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2028 – H2 2029
Medium confidencewindow, not a prediction
Project verification
Grid-backed
Construction documented by satellite imagery; grid record on file.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
DTE Electric · MISO
Substation: Not identified

Power reality

Announced
1.4 GW[3]
Reported by Edison Electric Institute
Interconnection request
No record
Contracted / approved
1.38 GW[4]
Reported utility / power contract
Under construction
1.38 GW[1]
Buildings 1–3 under construction (satellite-tracked phases)
Operational
No record
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2025-12-04 (0.8 years).
  • Stated date: Next projected milestone: 2028-12-31 (modeled/speculative)[1]
  • Required: 1.4 GW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2028 – H2 2029

Project verification

Development
  1. AnnouncedSep 11, 2026
    News report · Utility filing / announcement
    • Planned capacity reported: 1400 MW[5]
    • Sep 11, 2026 · Planned capacity reported: 1400 MW[3]
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contractDec 18, 2025
    Government record
    • Dec 18, 2025 · Contracted / committed power: 1383 MW[4]
    • Dec 18, 2025 · Interconnection agreement / service contract executed[4]
Build & energization
  1. Financing
  2. Under constructionDec 4, 2025
    Model estimate · Satellite imagery
    • Dec 4, 2025 · Reported status: under construction[1]
    • Dec 4, 2025 · Construction start[1]
    • Dec 4, 2025 · Land clearing begins for the entire site[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: News report, Utility filing / announcement, Government record, Model estimate, Satellite imagery.

Grid path

  1. facility
    OpenAI Stargate Michigan
  2. substation
    Not identified
    UnknownUnverified
    No substation mapped within 3 km and none named in filings.
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    DTE Electric[3][4][2][5]
    DocumentedConfirmed
    Named in a source
  5. ISO / RTO
    MISO[6]
    Service territoryLikely
    Balancing authority: MISO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
42.12209, -83.88516
County
Washtenaw County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Oracle[1]Confirmed
Developer

“Related Digital, a vertically integrated data center development and investment platform, today announced plans to develop a data center campus”

End user
OpenAI[1]Confirmed
Utility

“DTE Energy Open AI, Oracle, Related Digital / Data Center Saline Township, MI” Listed by EEI under this member utility.

Power (all fields)

Planned capacity
1.4 GW[3][5]Likely

“$7 billion data center campus with 1,400 MW of capacity.”

“the Stargate project’s expected 1.4 gigawatts of demand is equivalent to that of a large American city.”

Sources disagree. Also reported: 1.38 GW[1] (likely)
Contracted / committed power
1.38 GW[4]Confirmed

“1,383- megawatt (MW) data center in Saline Township” — Load under the DTE special contracts approved by the Michigan PSC (Case U-21990).

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
MISO[6]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
MISO[7]Likelyderived

Control area of the containing utility territory.

Contracted / committed power
1.38 GW[4]Confirmed

“1,383- megawatt (MW) data center in Saline Township” — Load under the DTE special contracts approved by the Michigan PSC (Case U-21990).

State avg. industrial price
9.81¢/kWh[9]Confirmed

Michigan statewide average, July 2026.

State avg. commercial price
16.46¢/kWh[9]Confirmed

Michigan statewide average, July 2026.

Generation within 50 km
1.07 GW[10]Confirmedderived

16 EIA-reported plants within 50 km.

Generation queued in county
2.97 GW[8]Confirmedderived

13 active generation interconnection requests in Washtenaw County: Gas 1,414 MW, Solar 884 MW, Storage 520 MW, Unknown 152 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Cement City Solar, LLC · AES Distributed EnergyPower plant (Solar)21.1 km20 MW[10]
University of Michigan · University of MichiganPower plant (Natural Gas)21.6 km57 MW[10]
Blue Elk IV Solar, LLC · Blue Elk IV Solar, LLCPower plant (Solar)23.6 km20 MW[10]
Superior · DTE Electric CompanyPower plant (Petroleum)25.5 km52 MW[10]
Letts Creek Solar, LLC · AES Distributed EnergyPower plant (Solar)26.7 km15 MW[10]
Sumpter · Wolverine Power Supply CoopPower plant (Natural Gas)29.6 km308 MW[10]
Grs Arbor Hills · Gas Recovery Systems IncPower plant (Biomass)40.6 km24 MW[10]
Jackson Generating Station · Consumers Energy Co - (MI)Power plant (Natural Gas)42.9 km534 MW[10]
Largest queued generation in this countyFuelQueue statusMWSource
J3923 at Majestic-Milan 345 kV LineMISO J3923GasIn study · proposed 2030-031.41 GW[8]
J3945 at MAJESTIC - MILAN 345.0kVMISO J3945SolarIn study · proposed 2030-01245 MW[8]
J1062 at Majestic - Lemoyne 345 kV Line TapMISO J1062SolarIA signed · proposed 2021-10200 MW[8]
J799 at Milan - Pioneer 120kV Line TapMISO J799SolarUnder construction · proposed 2019-09189 MW[8]
J1224 at Majestic - Milan 345 kV Line TapMISO J1224SolarUnder construction · proposed 2022-10170 MW[8]
J3654 at Line tap on Superior-Wayne 120kV line at 42.275480, -83.628250MISO J3654StorageIn study · proposed 2028-06150 MW[8]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Dec 4, 2025[1]
  5. First operational
    Dec 31, 2028[1]
    Projected
  6. Expected completion
    Dec 31, 2028[1]
    Projected
Planned capacity
1.4 GW[3][5]Likely

“$7 billion data center campus with 1,400 MW of capacity.”

“the Stargate project’s expected 1.4 gigawatts of demand is equivalent to that of a large American city.”

Sources disagree. Also reported: 1.38 GW[1] (likely)
Buildings (planned)
2[1]Likelyderived

Count of building outlines traced on satellite imagery.

Sources disagree. Also reported: 3[2] (likely)
Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–3under construction1.38 GWDec 31, 2028 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Site area
250 acres[2]LikelyAI-extracted

“The state-of-the-art data center campus, which is being developed on 250 acres in Saline Township”

Sources disagree. Also reported: 575 acres[5] (likely)
Capital cost / investment
$7B[5]LikelyAI-extracted

“$7 billion Stargate facility”

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
1.65M sq ft[2]LikelyAI-extracted

“consists of three 550,000 square-feet single-story buildings.”

Compute

Project
Stargate[1][2]Confirmed

“OpenAI, Oracle, and Related Digital Announce Stargate Data Center Site in Michigan”

What changed (last 3 years)

Follow this facility (RSS)
  • Planned capacity
    1.4 GW[5]→1.38 GWMar 12, 2026[1]→1.4 GWSep 11, 2026[3]
  • Buildings (planned)
    3Oct 30, 2025[2]→2Mar 12, 2026[1]
  • Status
    Planned[5]→PlannedOct 30, 2025[2]→Under constructionDec 4, 2025[1]

Timeline

Construction start: Dec 4, 2025[1]
First operational: Dec 31, 2028[1]
  1. Dec 4, 2025[1]

    Land clearing begins for the entire site

  2. Jan 20, 2026[1]

    Land clearing continues for all buildings (1-3)

  3. Mar 12, 2026[1]

    Groundwork is visible for Building 1, at the left end of the site.

  4. Dec 31, 2028Projected1.38 GW facility power· 3 buildings operational[1]

    Buildings 1-3 operational. Based on when maximum power load will be provided by DTE energy (Dec 2027), which can be extended by a year. Source, page 3

All claims (provenance audit)

39
FieldValueSourceConfidenceAs ofStatus
NameOpenAI Stargate Michigan[1] Likely2026-03-12Shown
StatusUnder construction[1] derivedLikely2025-12-04Superseded / alternative
StatusUnder construction[1] derivedLikely2026-01-20Superseded / alternative
StatusUnder construction[1] derivedLikely2026-03-12Shown
StatusPlanned[2] AI-extractedLikely2025-10-30Superseded / alternative
StatusPlanned[5] AI-extractedLikelySuperseded / alternative
Facility typeAI campus[1] derivedLikely2026-03-12Shown
ProjectStargate[1] Confirmed2026-03-12Shown
ProjectStargate[2] AI-extractedLikely2025-10-30Shown
OwnerOracleOwner: Oracle[1] Confirmed2026-03-12Shown
DeveloperRelated Digital[2] AI-extractedLikely2025-10-30Shown
End usersOpenAIUsers: OpenAI[1] Confirmed2026-03-12Shown
UtilityDTE Electric[3] Confirmed2026-09-11Shown
UtilityDTE Electric[4] Confirmed2025-12-18Shown
UtilityDTE Electric[2] AI-extractedLikely2025-10-30Shown
UtilityDTE Electric[5] AI-extractedLikely2025-12-18Shown
Planned capacity1.38 GW[1] estimatedLikely2026-03-12Superseded / alternative
Planned capacity1.4 GW[3] Likely2026-09-11Shown
Planned capacity1.4 GW[5] AI-extractedLikelyShown
Contracted / committed power1.38 GW[4] Confirmed2025-12-18Shown
ISO / RTOMISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC..[6] derivedLikely—Shown
Balancing authorityMISO[7] derivedLikely—Shown
Generation queued in county2.97 GW[8] derivedConfirmed2026-09-27Shown
State avg. industrial price9.81¢/kWh[9] Confirmed2026-07Shown
State avg. commercial price16.46¢/kWh[9] Confirmed2026-07Shown
Generation within 50 km1.07 GW[10] derivedConfirmed202502Shown
Buildings (planned)2[1] derivedLikely2026-03-12Shown
Buildings (planned)3[2] AI-extractedLikely2025-10-30Superseded / alternative
Buildings operational0[1] estimatedLikely2026-03-12Shown
Buildings operational0[1] estimatedLikely2025-12-04Superseded / alternative
Buildings operational0[1] estimatedLikely2026-01-20Superseded / alternative
Floor area1.65M sq ft[2] AI-extractedLikely2025-10-30Shown
Site area250 acres[2] AI-extractedLikely2025-10-30Shown
Site area575 acres[5] AI-extractedLikelySuperseded / alternative
Capital cost / investment$7B[5] AI-extractedLikelyShown
Construction startDec 4, 2025[1] derivedLikely2026-03-12Shown
First operationalDec 31, 2028[1] estimatedSpeculative2026-03-12Shown
Interconnection agreement / service contractDec 18, 2025[4] Confirmed2025-12-18Shown
Expected completionDec 31, 2028[1] estimatedSpeculative2026-03-12Shown