OpenAI Stargate Milam
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ Construction is documented, but no grid record or phase capacity yet backs the 1.2 GW announced.
- ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityOpenAI Stargate Milam
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityBluebonnet Electric Coop, INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- Orion I Solar Project (Solar, 200 MW) is 0.9 km away[6]EIA plant within 1.5 km; proximity does not establish that it supplies the facilitySolarCo-located200 MWUnverified
Location & imagery
Mapped outline- Coordinates
- 30.99625, -97.01069
- County
- Milam County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 5 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Entergy Texas INC., Heart of Texas Electric Coop, Bartlett Electric Coop, INC, Oncor Electric Delivery Company LLC.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2028-12-31); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside overlapping MISO and ERCOT footprints; chosen by the balancing areas of the overlapping utilities.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
20 EIA-reported plants within 50 km.
- Generation queued in county
22 active generation interconnection requests in Milam County: Storage 2,651 MW, Solar 2,337 MW, Gas 2,138 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Orion I Solar Project · Ben Milam Solar 1 LLC | Power plant (Solar) | 0.9 km | 200 MW | [6] |
| Orion II Solar Project · Ben Milam Solar 2 LLC | Power plant (Solar) | 8.1 km | 250 MW | [6] |
| Orion III Solar Project · Ben Milam Solar 3 LLC | Power plant (Solar) | 11.6 km | 250 MW | [6] |
| Five Wells Solar Center - Hybrid · Five Wells Solar Center, LLC | Power plant (Solar) | 23.7 km | 579 MW | [6] |
| Big Elm Solar · Big Elm Solar, LLC | Power plant (Solar) | 25.4 km | 200 MW | [6] |
| Temple Power Station · Temple Generation Holdings LLC | Power plant (Natural Gas) | 30 km | 1.58 GW | [6] |
| Major Oak Power · Major Oak Power, LLC | Power plant (Coal) | 31.9 km | 305 MW | [6] |
| Bpl Crown Solar LLC · BPL Crown Solar LLC | Power plant (Solar) | 39.6 km | 100 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Sandow Lakes Energy StationERCOT 27INR0071 · SL Energy Power Plant I, LLC | Gas | In study · proposed 2028-04 | 1.29 GW | [4] |
| MilamStation Power Secured Gas GenerationERCOT 29INR0120 · LCC-TX8, LLC | Gas | In study · proposed 2029-09 | 846 MW | [4] |
| Scorpius SolarERCOT 26INR0609 · Ben Milam Solar 4 | Solar | In study · proposed 2029-06 | 600 MW | [4] |
| Betel Storage IERCOT 26INR0630 · BETEL STORAGE I | Storage | In study · proposed 2026-08 | 500 MW | [4] |
| Betel Storage IIERCOT 26INR0633 · BETEL STORAGE II | Storage | In study · proposed 2026-12 | 500 MW | [4] |
| Aquila SolarERCOT 26INR0635 · Ben Milam Solar 5 | Solar | In study · proposed 2026-11 | 500 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startSep 27, 2025[1]
- First operational—
- Expected completionDec 31, 2028[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2028-12-31); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | planned | — | Outlines traced on imagery; no completion date projected yet | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Project
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Sep 27, 2025[1]
Land clearing begins for the site
- Jan 4, 2026[1]
Small sections of building foundation construction begins, and land clearing appears to be mostly finished
- Mar 23, 2026[1]
Steel framing and roofing is underway for Building 1.
All buildings finished, site is fully operational. Our reasoning is that examples so far take a median of 2-2.5 years to go from land clearing to 1 GW. This suggests around 2028-01-01 here. However, due to delays being more likely than speedups and the fact that this base rate data is still unproven, the more conservative estimate is made. The current state of the site also supports this estimation.
All claims (provenance audit)
22| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | OpenAI Stargate Milam | [1] | Likely | 2026-03-23 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-09-27 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-01-04 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-03-23 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-03-23 | Shown |
| Project | Stargate | [1] | Confirmed | 2026-03-23 | Shown |
| Owner | SoftBankOwner: Softbank | [1] | Confirmed | 2026-03-23 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Confirmed | 2026-03-23 | Shown |
| Utility | Bluebonnet Electric Coop, INCterritory 1892: BLUEBONNET ELECTRIC COOP, INC (COOPERATIVE, BLUEBONNET ELECTRIC | [2] derived | Unverified | 2022 | Shown |
| Planned capacity | 1.2 GW | [1] estimated | Likely | 2026-03-23 | Shown |
| ISO / RTO | ERCOTMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | ELECTRIC RELIABIL | [3] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Generation queued in county | 7.13 GW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.73 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-03-23 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-03-23 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-09-27 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-01-04 | Superseded / alternative |
| Construction start | Sep 27, 2025 | [1] derived | Likely | 2026-03-23 | Shown |
| Expected completion | Dec 31, 2028 | [1] estimated | Speculative | 2026-03-23 | Shown |