OpenAI Stargate Milam

Under constructionAI campusCampusMilam County, Texas
40% profile completeness
22 claims from 9 sources
Current facility power
Not yet sourced
Planned capacity
1.2 GW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2028 – H2 2029
Medium confidencewindow, not a prediction
Project verification
Under construction
Construction documented by satellite imagery.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
Bluebonnet Electric Coop, INC · ERCOT
Substation: Not identified

Power reality

Announced
1.2 GW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
  • ⚠ Construction is documented, but no grid record or phase capacity yet backs the 1.2 GW announced.
  • ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2025-09-27 (1.0 years).
  • Stated date: Modeled completion date: 2028-12-31 (modeled/speculative)[1]
  • Required: 1.2 GW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2028 – H2 2029

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionSep 27, 2025
    Model estimate · Satellite imagery
    • Sep 27, 2025 · Reported status: under construction[1]
    • Sep 27, 2025 · Construction start[1]
    • Sep 27, 2025 · Land clearing begins for the site[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    OpenAI Stargate Milam
  2. substation
    Not identified
    UnknownUnverified
    No substation mapped within 3 km and none named in filings.
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Bluebonnet Electric Coop, INC[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    ERCOT[3]
    Service territoryLikely
    Balancing authority: ERCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

  • Orion I Solar Project (Solar, 200 MW) is 0.9 km away[6]
    EIA plant within 1.5 km; proximity does not establish that it supplies the facility
    SolarCo-located200 MWUnverified

Location & imagery

Mapped outline
Coordinates
30.99625, -97.01069
County
Milam County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
SoftBank[1]Confirmed
End user
OpenAI[1]Confirmed
Utility

Most likely retail provider among 5 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Entergy Texas INC., Heart of Texas Electric Coop, Bartlett Electric Coop, INC, Oncor Electric Delivery Company LLC.

Power (all fields)

Planned capacity
1.2 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-12-31); not necessarily full build-out.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
ERCOT[3]Likelyderived

Location falls inside overlapping MISO and ERCOT footprints; chosen by the balancing areas of the overlapping utilities.

Balancing authority
ERCO[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
7.07¢/kWh[5]Confirmed

Texas statewide average, July 2026.

State avg. commercial price
8.47¢/kWh[5]Confirmed

Texas statewide average, July 2026.

Generation within 50 km
3.73 GW[6]Confirmedderived

20 EIA-reported plants within 50 km.

Generation queued in county
7.13 GW[4]Confirmedderived

22 active generation interconnection requests in Milam County: Storage 2,651 MW, Solar 2,337 MW, Gas 2,138 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Orion I Solar Project · Ben Milam Solar 1 LLCPower plant (Solar)0.9 km200 MW[6]
Orion II Solar Project · Ben Milam Solar 2 LLCPower plant (Solar)8.1 km250 MW[6]
Orion III Solar Project · Ben Milam Solar 3 LLCPower plant (Solar)11.6 km250 MW[6]
Five Wells Solar Center - Hybrid · Five Wells Solar Center, LLCPower plant (Solar)23.7 km579 MW[6]
Big Elm Solar · Big Elm Solar, LLCPower plant (Solar)25.4 km200 MW[6]
Temple Power Station · Temple Generation Holdings LLCPower plant (Natural Gas)30 km1.58 GW[6]
Major Oak Power · Major Oak Power, LLCPower plant (Coal)31.9 km305 MW[6]
Bpl Crown Solar LLC · BPL Crown Solar LLCPower plant (Solar)39.6 km100 MW[6]
Largest queued generation in this countyFuelQueue statusMWSource
Sandow Lakes Energy StationERCOT 27INR0071 · SL Energy Power Plant I, LLCGasIn study · proposed 2028-041.29 GW[4]
MilamStation Power Secured Gas GenerationERCOT 29INR0120 · LCC-TX8, LLCGasIn study · proposed 2029-09846 MW[4]
Scorpius SolarERCOT 26INR0609 · Ben Milam Solar 4SolarIn study · proposed 2029-06600 MW[4]
Betel Storage IERCOT 26INR0630 · BETEL STORAGE IStorageIn study · proposed 2026-08500 MW[4]
Betel Storage IIERCOT 26INR0633 · BETEL STORAGE IIStorageIn study · proposed 2026-12500 MW[4]
Aquila SolarERCOT 26INR0635 · Ben Milam Solar 5SolarIn study · proposed 2026-11500 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Sep 27, 2025[1]
  5. First operational
    —
  6. Expected completion
    Dec 31, 2028[1]
    Projected
Planned capacity
1.2 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-12-31); not necessarily full build-out.

Buildings (planned)
1[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1planned—Outlines traced on imagery; no completion date projected yet[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Project
Stargate[1]Confirmed

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

Construction start: Sep 27, 2025[1]
  1. Sep 27, 2025[1]

    Land clearing begins for the site

  2. Jan 4, 2026[1]

    Small sections of building foundation construction begins, and land clearing appears to be mostly finished

  3. Mar 23, 2026[1]

    Steel framing and roofing is underway for Building 1.

  4. Dec 31, 2028Projected1.2 GW facility power[1]

    All buildings finished, site is fully operational. Our reasoning is that examples so far take a median of 2-2.5 years to go from land clearing to 1 GW. This suggests around 2028-01-01 here. However, due to delays being more likely than speedups and the fact that this base rate data is still unproven, the more conservative estimate is made. The current state of the site also supports this estimation.

All claims (provenance audit)

22
FieldValueSourceConfidenceAs ofStatus
NameOpenAI Stargate Milam[1] Likely2026-03-23Shown
StatusUnder construction[1] derivedLikely2025-09-27Superseded / alternative
StatusUnder construction[1] derivedLikely2026-01-04Superseded / alternative
StatusUnder construction[1] derivedLikely2026-03-23Shown
Facility typeAI campus[1] derivedLikely2026-03-23Shown
ProjectStargate[1] Confirmed2026-03-23Shown
OwnerSoftBankOwner: Softbank[1] Confirmed2026-03-23Shown
End usersOpenAIUsers: OpenAI[1] Confirmed2026-03-23Shown
UtilityBluebonnet Electric Coop, INCterritory 1892: BLUEBONNET ELECTRIC COOP, INC (COOPERATIVE, BLUEBONNET ELECTRIC [2] derivedUnverified2022Shown
Planned capacity1.2 GW[1] estimatedLikely2026-03-23Shown
ISO / RTOERCOTMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | ELECTRIC RELIABIL[3] derivedLikely—Shown
Balancing authorityERCO[2] derivedLikely—Shown
Generation queued in county7.13 GW[4] derivedConfirmed2026-09-01Shown
State avg. industrial price7.07¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price8.47¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km3.73 GW[6] derivedConfirmed202502Shown
Buildings (planned)1[1] derivedLikely2026-03-23Shown
Buildings operational0[1] estimatedLikely2026-03-23Shown
Buildings operational0[1] estimatedLikely2025-09-27Superseded / alternative
Buildings operational0[1] estimatedLikely2026-01-04Superseded / alternative
Construction startSep 27, 2025[1] derivedLikely2026-03-23Shown
Expected completionDec 31, 2028[1] estimatedSpeculative2026-03-23Shown