OpenAI Stargate New Mexico
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityOpenAI Stargate New Mexico
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityNot identifiedUnknownUnverified
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
County-level (approximate)Location is approximate (county-level (approximate)); the marker does not identify the exact site.
- Coordinates
- 32.35177, -106.83241
- County
- Doña Ana County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2028-12-31); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
New Mexico statewide average, July 2026.
- State avg. commercial price
New Mexico statewide average, July 2026.
- Generation within 50 km
5 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Nmsu Solar and Storage · El Paso Electric Co | Power plant (Solar) | 11 km | 4 MW | [5] |
| Sune Epe2 LLC · SunE EPE2, LLC | Power plant (Solar) | 13.5 km | 14 MW | [5] |
| Afton Generating Station · Public Service Co of NM | Power plant (Natural Gas) | 26.5 km | 239 MW | [5] |
| Wsmr I · Siemens Government Technologies Inc | Power plant (Solar) | 33.7 km | 5 MW | [5] |
| New Mexico State University · New Mexico State University | Power plant (Natural Gas) | 41.4 km | 5 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startOct 1, 2025[1]
- First operationalDec 31, 2028[1]Projected
- Expected completionDec 31, 2028[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2028-12-31); not necessarily full build-out.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Buildings 1–4 | under construction | 2.45 GW | Dec 31, 2028 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Project
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Oct 1, 2025[1]
Construction and land clearing begins
- Feb 6, 2026[1]
Land clearing continues, foundation construction begins 2 of the main buildings (Building B & D). Construction also beginning on modular chiller plants.
- Jun 22, 2026[1]
Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large solar array and water storage basins are visible on site, and two cleared areas on the western side of the campus, likely for on-site power generation. No buildings appear operational yet (no completed roofs or signs of active cooling), consistent with the projected 2028 completion.
Estimated construction completion date of the site. Stormwater permitting says 2027-12-31 for stormwater construction to finish, but for a more conservative estimate and based on the current state of the site, we pushed the final date by a year beyond it. Source, page 2
All claims (provenance audit)
21| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | OpenAI Stargate New Mexico | [1] | Likely | 2026-06-22 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-10-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-02-06 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-06-22 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-22 | Shown |
| Project | Stargate | [1] | Confirmed | 2026-06-22 | Shown |
| Owner | OracleOwner: Oracle | [1] | Confirmed | 2026-06-22 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Confirmed | 2026-06-22 | Shown |
| Energy partners | Bloom EnergyEnergy companies: Bloom Energy | [1] | Confirmed | 2026-06-22 | Shown |
| Planned capacity | 2.45 GW | [1] estimated | Likely | 2026-06-22 | Shown |
| ISO / RTO | None (non-RTO region) | [2] derived | Likely | — | Shown |
| Balancing authority | EPE | [3] derived | Likely | — | Shown |
| State avg. industrial price | 4.16¢/kWh | [4] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.90¢/kWh | [4] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 265 MW | [5] derived | Confirmed | 202502 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-06-22 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-02-06 | Superseded / alternative |
| Construction start | Oct 1, 2025 | [1] derived | Likely | 2026-06-22 | Shown |
| First operational | Dec 31, 2028 | [1] estimated | Speculative | 2026-06-22 | Shown |
| Expected completion | Dec 31, 2028 | [1] estimated | Speculative | 2026-06-22 | Shown |