OpenAI Stargate Shackelford
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — ERCOT does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityOpenAI Stargate Shackelford
- →substationOn-site substation[1]Satellite imageryLikely1 substation outline traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityTaylor Electric Coop INC - (Tx)[3]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 32.54405, -99.54824
- Address
- County
- Shackelford County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Developer
“Together with Frontier, a Texas campus in Shackelford County, Vantage is investing more than $40 billion in critical digital infrastructure, underscoring the company’s accelerating momentum to deliver high-density, next-generation digital infrastructure at unprecedented scale and speed for today’s most advanced global tech leaders.”
- Utility
Most likely retail provider among 6 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Big Country Electric Coop, INC, Comanche County Elec Coop Assn, Oncor Electric Delivery Company LLC, AEP Texas North Company, Fort Belknap Electric Coop INC.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2028-11-11); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
12 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Shackelford County: Storage 207 MW, Solar 204 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Mesquite Wind Power LLC · Mesquite Wind LLC | Power plant (Wind) | 10.5 km | 200 MW | [7] |
| Post Oak Wind LLC · Mesquite Wind LLC | Power plant (Wind) | 10.7 km | 200 MW | [7] |
| Hackberry Wind Farm · Hackberry Wind LLC | Power plant (Wind) | 27.6 km | 162 MW | [7] |
| Bmp Wind (Tx) · BMP Wind LLC | Power plant (Wind) | 37.2 km | 340 MW | [7] |
| Century Oak Wind Project, LLC · Century Oak Wind Project, LLC | Power plant (Wind) | 38.7 km | 152 MW | [7] |
| Roadrunner Wind Farm · Roadrunner Crossing Wind Farm, LLC | Power plant (Wind) | 42.9 km | 256 MW | [7] |
| Ranchland Wind Project II · Ranchland Wind Project II, LLC | Power plant (Wind) | 44.6 km | 148 MW | [7] |
| Anson Solar Center, LLC · Engie North America | Power plant (Solar) | 45.6 km | 200 MW | [7] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Shackleford BESSERCOT 26INR0500 · Shackelford County BESS LLC | Storage | In study · proposed 2028-09 | 207 MW | [5] |
| Chimney Creek SolarERCOT 28INR0151 · Chimney Creek Energy, LLC | Solar | In study · proposed 2030-05 | 204 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startAug 1, 2025[1]
- First operationalAug 15, 2027[1]Projected
- Expected completionNov 11, 2028[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2028-11-11); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | under construction | 196 MW | Aug 15, 2027 (projected) | [1] |
| Building 2 | under construction | 196 MW | Oct 19, 2027 (projected) | [1] |
| Building 3 | under construction | 196 MW | Nov 18, 2027 (projected) | [1] |
| Building 4 | under construction | 196 MW | Feb 11, 2028 (projected) | [1] |
| Building 5 | under construction | 196 MW | Mar 8, 2028 (projected) | [1] |
| Building 6 | under construction | 196 MW | Apr 4, 2028 (projected) | [1] |
| Building 7 | under construction | 196 MW | May 12, 2028 (projected) | [1] |
| Building 8 | under construction | 196 MW | Oct 17, 2028 (projected) | [1] |
| Building 9 | under construction | 196 MW | Oct 18, 2028 (projected) | [1] |
| Building 10 | under construction | 196 MW | Nov 11, 2028 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Aug 1, 2025[1]
Land clearing begins.
- Jan 18, 2026[1]
The layout of Buildings 1-5 is visible. Steel framing has just started on Building 1.
- Apr 14, 2026[1]
Steel framing is underway for Buildings 1-3, and roofing is underway for Building 1.
- Sep 4, 2026[1]
Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.
Building 1 is operational (estimate). TDLR lists the construction completion date for Building 1 as 2027-02-15. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 2 is operational (estimate). TDLR lists the construction completion date for Building 2 as 2027-04-19. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 3 is operational (estimate). TDLR lists the construction completion date for Building 3 as 2027-05-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 4 is operational (estimate). TDLR lists the construction completion date for Building 4 as 2027-08-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 5 is operational (estimate). TDLR lists the construction completion date for Building 5 as 2027-09-08. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 6 is operational (estimate). TDLR lists the construction completion date for Building 6 as 2027-10-04. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 7 is operational (estimate). TDLR lists the construction completion date for Building 7 as 2027-11-12. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 8 is operational (estimate). TDLR lists the construction completion date for Building 8 as 2028-04-17. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 9 is operational (estimate). TDLR lists the construction completion date for Building 9 as 2028-04-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
Building 10 is operational (estimate). TDLR lists the construction completion date for Building 10 as 2028-05-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.
All claims (provenance audit)
30| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | OpenAI Stargate Shackelford | [1] | Likely | 2026-09-04 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-08-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-01-18 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-04-14 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-09-04 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-09-04 | Shown |
| Project | Stargate | [1] | Confirmed | 2026-09-04 | Shown |
| Address | 175 Private Road 1604, Abilene, TX 79601, Shackelford County | [1] | Likely | 2026-09-04 | Shown |
| Owner | OracleOwner: Oracle | [1] | Confirmed | 2026-09-04 | Shown |
| Developer | Vantage Data Centers | [2] AI-extracted | Likely | 2026-09-27 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Confirmed | 2026-09-04 | Shown |
| Utility | Taylor Electric Coop INC - (Tx)territory 27369: TAYLOR ELECTRIC COOP INC - (TX) (COOPERATIVE, TAYLOR ELECTRIC C | [3] derived | Unverified | 2022 | Shown |
| Investors | OracleInvestors: Oracle | [1] | Confirmed | 2026-09-04 | Shown |
| Investors | OpenAIInvestors: OpenAI | [1] | Confirmed | 2026-09-04 | Shown |
| Planned capacity | 1.96 GW | [1] estimated | Likely | 2026-09-04 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [4] derived | Likely | — | Shown |
| Balancing authority | ERCO | [3] derived | Likely | — | Shown |
| Generation queued in county | 410 MW | [5] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.85 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 10 | [1] derived | Likely | 2026-09-04 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-09-04 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-08-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-01-18 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-04-14 | Superseded / alternative |
| Chip types | Rubin | [1] | Confirmed | 2026-09-04 | Shown |
| Construction start | Aug 1, 2025 | [1] derived | Likely | 2026-09-04 | Shown |
| First operational | Aug 15, 2027 | [1] estimated | Speculative | 2026-09-04 | Shown |
| Expected completion | Nov 11, 2028 | [1] estimated | Speculative | 2026-09-04 | Shown |