OpenAI Stargate Wisconsin
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application2026
News report
- 2026 · proposed $1.4B transmission line from American Transmission Co.[2]
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: News report, Utility filing / announcement, Model estimate, Satellite imagery.
Grid path
- →facilityOpenAI Stargate Wisconsin
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- Vantage funding $175 million of regional infrastructure upgrades[4]
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 43.43160, -87.85642
- County
- Ozaukee County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Developer
“Vantage Data Centers, which was previously the only known company behind the project, had originally said it would spend $8 billion on the development.”
- Utility
“We Energies (WEC Energy Group) OpenAI, Oracle, Vantage Data Centers / Data Center Port Washington, WI” Listed by EEI under this member utility.
- Energy partner
“Vantage is underwriting 100% of the power infrastructure investment with a dedicated electricity rate from WEC Energy Group utility We Energies.”
Power (all fields)
- Planned capacity
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Interconnection status
“A $1.4 billion transmission line project from American Transmission Co. is being proposed to help support the project.”
- Required grid upgrades
“Vantage will invest $175 million in regional infrastructure upgrades.”
- State avg. industrial price
Wisconsin statewide average, July 2026.
- State avg. commercial price
Wisconsin statewide average, July 2026.
- Generation within 50 km
17 EIA-reported plants within 50 km.
- Generation queued in county
1 active generation interconnection requests in Ozaukee County: Storage 200 MW. Queued projects often don't get built.
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Port Washington Generating Station · Wisconsin Electric Power Co | Power plant (Natural Gas) | 5.4 km | 1.24 GW | [9] |
| Onion River · Wisconsin Power & Light Co | Power plant (Solar) | 19 km | 150 MW | [9] |
| Edgewater · Wisconsin Power & Light Co | Power plant (Coal) | 33.8 km | 405 MW | [9] |
| Germantown · Wisconsin Electric Power Co | Power plant (Petroleum) | 35.4 km | 255 MW | [9] |
| Sheboygan Falls · Wisconsin Power & Light Co | Power plant (Natural Gas) | 35.6 km | 298 MW | [9] |
| Valley (Wi) · Wisconsin Electric Power Co | Power plant (Natural Gas) | 45 km | 267 MW | [9] |
| Mmsd Jones Island Wastewater · Milwaukee Metro Sewerage Dist | Power plant (Natural Gas) | 45.8 km | 27 MW | [9] |
| Cedar Ridge · Wisconsin Power & Light Co | Power plant (Wind) | 47.9 km | 68 MW | [9] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J3784 at Saukville (Cedarsauk)MISO J3784 | Storage | In study · proposed 2028-06 | 200 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- AnnouncedOct 22, 2025[3]
- Land acquired—
- Permitting—
- Construction startJan 2, 2026[1]
- First operationalDec 31, 2028[1]Projected
- Expected completion
- Planned capacity
- Buildings (planned)
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Buildings 1–4 | under construction | 1.3 GW | Dec 31, 2028 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Site area
- Capital cost / investment
“they now plan to invest more than $15 billion at the campus”
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Jan 2, 2026[1]
Ground broken for the facility, land clearing begins for all buildings
- Feb 14, 2026[1]
Land clearing continues, foundation construction clearly begins for eastern and northern buildings (Building 1-2)
- Jul 24, 2026[1]
Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.
Building 4 and supporting facilities/buildings operational, whole facility now operational. Based on the environmental analysis (page 6) filed for the site.
All claims (provenance audit)
42| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | OpenAI Stargate Wisconsin | [1] | Likely | 2026-07-24 | Shown |
| Status | Under construction | [1] derived | Likely | 2026-01-02 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-02-14 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-07-24 | Shown |
| Status | Planned | [2] AI-extracted | Likely | 2026 | Superseded / alternative |
| Facility type | AI campus | [1] derived | Likely | 2026-07-24 | Shown |
| Project | Stargate | [1] | Confirmed | 2026-07-24 | Shown |
| Project | Stargate | [2] AI-extracted | Likely | 2026 | Shown |
| Owner | OracleOwner: Oracle | [1] | Confirmed | 2026-07-24 | Shown |
| Developer | Vantage Data Centers | [2] AI-extracted | Likely | 2025-10-23 | Shown |
| Developer | Vantage Data Centers | [3] AI-extracted | Likely | 2026-09-27 | Shown |
| End users | OpenAIUsers: OpenAI | [1] | Confirmed | 2026-07-24 | Shown |
| Utility | We Energies | [4] | Confirmed | 2026-09-11 | Shown |
| Utility | We Energies | [2] AI-extracted | Likely | 2025-10-23 | Shown |
| Energy partners | WEC Energy Group | [3] AI-extracted | Likely | 2026-09-27 | Shown |
| Investors | OpenAI | [2] AI-extracted | Likely | 2025-10-23 | Shown |
| Planned capacity | 1.3 GW | [1] estimated | Likely | 2026-07-24 | Shown |
| Planned capacity | 1.3 GW | [4] | Likely | 2026-09-11 | Shown |
| Planned capacity | 1.3 GW | [2] AI-extracted | Likely | 2026 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [5] derived | Likely | — | Shown |
| Balancing authority | MISO | [6] derived | Likely | — | Shown |
| Interconnection status | proposed $1.4B transmission line from American Transmission Co. | [2] AI-extracted | Likely | 2026 | Shown |
| Required grid upgrades | Vantage funding $175 million of regional infrastructure upgrades | [4] | Likely | 2026-09-11 | Shown |
| Generation queued in county | 200 MW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.46¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.93¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.74 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-07-24 | Shown |
| Buildings (planned) | 4 | [2] AI-extracted | Likely | 2026 | Superseded / alternative |
| Buildings (planned) | 4 | [3] AI-extracted | Likely | 2026-09-27 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-07-24 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-01-02 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-02-14 | Superseded / alternative |
| Site area | 670 acres | [2] AI-extracted | Likely | 2026 | Superseded / alternative |
| Site area | 672 acres | [3] AI-extracted | Likely | 2026-09-27 | Shown |
| Capital cost / investment | $15B | [2] AI-extracted | Likely | 2026 | Shown |
| Announced | Oct 22, 2025 | [3] AI-extracted | Likely | 2026-09-27 | Shown |
| Construction start | Jan 2, 2026 | [1] derived | Likely | 2026-07-24 | Shown |
| First operational | Dec 31, 2028 | [1] estimated | Speculative | 2026-07-24 | Shown |
| Expected completion | Dec 31, 2028 | [1] estimated | Speculative | 2026-07-24 | Superseded / alternative |
| Expected completion | 2028 | [2] AI-extracted | Likely | 2026 | Shown |
| Expected completion | 2028 | [3] AI-extracted | Likely | 2026-09-27 | Shown |