What changed — Indiana
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Jun 4, 2026Meta Jeffersonville · IN
- Buildings operational: 0 → 2
- Status: Under construction → Operating
- New capacity online: Building 1 and 2 are operational.
Source: Epoch AI - Mar 23, 2026Anthropic-Amazon New Carlisle · IN
- Current IT capacity: 626 MW → 910 MW
- Current facility power: 751 MW → 1.09 GW
- Buildings operational: 11 → 16
- New capacity online: Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.
Source: Epoch AI - Dec 23, 2025Anthropic-Amazon New Carlisle · IN
- Current IT capacity: 398 MW → 626 MW
- Current facility power: 478 MW → 751 MW
- Buildings operational: 7 → 11
- New capacity online: Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.
Source: Epoch AI - Jun 23, 2025Anthropic-Amazon New Carlisle · IN
- Buildings operational: 0 → 7
- Status: Under construction → Operating + expanding
- New capacity online: Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.
Source: Epoch AI - Apr 1, 2024Google Fort Wayne · IN
- Construction started: First signs of development/land clearing
Source: Epoch AI - Feb 9, 2024Anthropic-Amazon New Carlisle · IN
- Construction started: Land clearing begins in the northern section
Source: Epoch AI - Feb 1, 2024