DC
/

What changed — Virginia

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. Jun 16, 2026
    Google Arcola · VA
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating
    • New capacity online: Building 1 is operational, based off of colored motion artifacts from cooling towers and direct visual verification.
    Source: Epoch AI
  2. May 20, 2026
    CoreWeave Chester VA · VA
    • Current IT capacity: 27 MW → 82 MW
    • Current facility power: 38 MW → 114 MW
    • Buildings operational: 1 → 2
    • New capacity online: Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans.
    Source: Epoch AI
  3. May 20, 2026
    Google Bristow · VA
    • Current IT capacity: 174 MW → 238 MW
    • Current facility power: 208 MW → 286 MW
    • Buildings operational: 2 → 3
    • Status: Operating + expanding → Operating
    • New capacity online: Building 3 is operational, based off of colored motion artifacts from cooling towers.
    Source: Epoch AI
  4. May 14, 2026
    QTS Richmond 2 · VA
    • Current IT capacity: 144 MW → 180 MW
    • Current facility power: 202 MW → 252 MW
    • Buildings operational: 4 → 5
    • Status: Operating + expanding → Operating
    • New capacity online: Building 5 is estimated to be operational, based on the previous entry.
    Source: Epoch AI
  5. May 14, 2026
    QTS Richmond 3 · VA
    • Current IT capacity: 48 MW → 144 MW
    • Current facility power: 67 MW → 202 MW
    • Buildings operational: 1 → 3
    • New capacity online: Building 2 and 3 are operational, based on the previous entry.
    Source: Epoch AI
  6. Mar 17, 2026
    Amazon IAD-500 · VA
    • Land acquired: Deed/transfer recorded for parcel 0242 14 0001 (no sale price disclosed).
  7. Mar 17, 2026
    Unnamed data center — Redskin Drive · VA
    • Land acquired: Deed/transfer recorded for parcel 0242 14 0002 (no sale price disclosed).
  8. Mar 17, 2026
    Unnamed data center — Redskin Drive · VA
    • Land acquired: Deed/transfer recorded for parcel 0242 14 0003 (no sale price disclosed).
  9. Feb 13, 2026
    QTS Richmond 1 · VA
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  10. Feb 13, 2026
    QTS Richmond 3 · VA
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars in the carpark, b…
    Source: Epoch AI
  11. Dec 31, 2025
    QTS Richmond 2 · VA
    • Current IT capacity: 72 MW → 144 MW
    • Current facility power: 101 MW → 202 MW
    • Buildings operational: 2 → 4
    • New capacity online: Building 3 and 4 are operational, based on the substation being completed earlier, the buildings looking complete, and carparks being moderately full. Building 5 still has construction work.
    Source: Epoch AI
  12. Nov 19, 2025
    QTS Richmond 1 · VA
    • Current IT capacity: 190 MW → 238 MW
    • Current facility power: 266 MW → 333 MW
    • Buildings operational: 4 → 5
    • New capacity online: Building 5 is operational, based on a complete building and full carpark in a Google Earth image. Construction equipment around Building 1 and 2 has cleared up again.
    Source: Epoch AI
  13. Sep 15, 2025
    Equinix DC7 · VA
    • Land acquired: Deed/transfer recorded for parcel 0392 01 0013D: $37,000,000.
  14. Jun 3, 2025
    QTS Richmond 1 · VA
    • Current IT capacity: 142 MW → 190 MW
    • Current facility power: 199 MW → 266 MW
    • Buildings operational: 3 → 4
    • New capacity online: Building 4 is operational, based on a complete building and full carpark in a Google Earth image. Building 5 does not seem quite operational given the empty carpark and construction activity at the perimeter.
    Source: Epoch AI
  15. May 6, 2025
    AWS · VA
    • Land acquired: Deed recorded for parcel 7595-85-3742.
  16. May 6, 2025
    STACK Infrastructure NVA02 · VA
    • Land acquired: Deed recorded for parcel 7595-65-9789.00.
  17. Apr 29, 2025
    Google Bristow · VA
    • Current IT capacity: 87 MW → 174 MW
    • Current facility power: 104 MW → 208 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.
    Source: Epoch AI
  18. Apr 23, 2025
    Menlo Digital MD-DC1 · VA
    • Land acquired: Deed/transfer recorded for parcel 0244 03 0002B (no sale price disclosed).
  19. Apr 10, 2025
    Unnamed data center · VA
    • Land acquired: Deed recorded for parcel 7596-61-8378.00.
  20. Apr 10, 2025
    Unnamed data center · VA
    • Land acquired: Deed recorded for parcel 7596-62-9148.00.
  21. Apr 1, 2025
    CoreSite VA2 · VA
    • Last recorded sale price: $44.5M → $53M
  22. Feb 4, 2025
    QTS Richmond 1 · VA
    • Current IT capacity: 94 MW → 142 MW
    • Current facility power: 132 MW → 199 MW
    • Buildings operational: 2 → 3
    • New capacity online: Building 3 is operational, based on the building looking complete and the carpark to the south being full. Three more backup generators added to the Building 1 and 2 area, with a lot more construction equipment again …
    Source: Epoch AI
  23. Feb 4, 2025
    QTS Richmond 2 · VA
    • Buildings operational: 0 → 2
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4 roof is partly completed.
    Source: Epoch AI
  24. Jan 22, 2025
    Amazon IAD-195 · VA
    • Land acquired: Deed recorded for parcel 7397-36-1468.
  25. Jan 22, 2025
    Amazon IAD-196 · VA
    • Land acquired: Deed recorded for parcel 7397-36-2834.
  26. Jan 22, 2025
    Amazon IAD-197 · VA
    • Land acquired: Deed recorded for parcel 7397-35-5597.
  27. 2025
    Equinix Ashburn DC18 · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2025-0027 — Active, 183,925 sq ft proposed.
  28. 2025
    Proposed data center — Amazon Data Services · VA
    • Permit / site plan approved: Loudoun County site plan EPLAN-2025-0012 — Approved, 550,000 sq ft proposed.
  29. 2025
    Proposed data center — Ashburn Village Office Park · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2025-0061 — Active, 469,479 sq ft proposed.
  30. 2025
    Proposed data center — Beaumeade · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2025-0028 — Active, 230,530 sq ft proposed.
  31. 2025
    Proposed data center — Cardinal Industrial Park · VA
    • Permit / site plan filed: Loudoun County site plan TLSPEX2025-0003 — Active, 315,000 sq ft proposed.
  32. 2025
    Proposed data center — EPLAN-2025-0126 · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2025-0126 — Active, 1,388,880 sq ft proposed.
  33. 2025
    Proposed data center — EPLAN-2025-0195 · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2025-0195 — Active, 751,902 sq ft proposed.
  34. 2025
    Proposed data center — Evergreen Meadows · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2025-0049 — Active, 191,000 sq ft proposed.
  35. 2025
    Proposed data center — Gateway North · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2025-0034 — Active, 3,161,378 sq ft proposed.
  36. 2025
    Proposed data center — Prologis Exchange · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2025-0102 — Active, 16,049 sq ft proposed.
  37. 2025
    Proposed data center — Sdc Ashburn · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2025-0015 — Active, 20,000 sq ft proposed.
  38. 2025
    Proposed data center — Stack Broad Run Land Condo · VA
    • Permit / site plan approved: Loudoun County site plan EPLAN-2025-0135 — Approved, 376,862 sq ft proposed.
  39. 2025
    Proposed data center — Sterling Business Park · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2025-0027 — Active, 315,582 sq ft proposed.
  40. Oct 7, 2024
    NTT VA10 · VA
    • Land acquired: Deed recorded for parcel 7397-56-8403 (owner of record: Ntt Global Data Centers Va10 LLC Attn: Legal Dept).
  41. Oct 1, 2024
    Google Arcola · VA
    • Construction started: Building 1 foundation started
    Source: Epoch AI
  42. Oct 1, 2024
    STACK Infrastructure NVA02 · VA
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery (a clear image of this c…
    Source: Epoch AI
  43. Jul 3, 2024
    STACK · VA
    • Land acquired: Deed recorded for parcel 7595-76-6544.00 (owner of record: Si Nva 04 LLC Attn Property Tax).
  44. Jun 25, 2024
    Amazon IAD-1 · VA
    • Land acquired: Deed/transfer recorded for parcel 0343 09 0004A (no sale price disclosed).
  45. Jun 25, 2024
    Amazon IAD-22 · VA
    • Land acquired: Deed/transfer recorded for parcel 0343 09 0004A (no sale price disclosed).
  46. Jun 23, 2024
    QTS Richmond 1 · VA
    • Current IT capacity: 47 MW → 94 MW
    • Current facility power: 66 MW → 132 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 (retrofitted) is operational. This is based on Building 2 looking compelte, and construction around Building 1 and 2 being mostly cleared. A colored motion artifact on one of the Building 1 cooling tower fa…
    Source: Epoch AI
  47. May 6, 2024
    Amazon IAD-500 · VA
    • Land acquired: Deed/transfer recorded for parcel 0242 14 0001 (no sale price disclosed).
  48. May 6, 2024
    Unnamed data center — Redskin Drive · VA
    • Land acquired: Deed/transfer recorded for parcel 0242 14 0002 (no sale price disclosed).
  49. May 6, 2024
    Unnamed data center — Redskin Drive · VA
    • Land acquired: Deed/transfer recorded for parcel 0242 14 0003 (no sale price disclosed).
  50. Apr 30, 2024
    CoreWeave Chester VA · VA
    • Current IT capacity: 18 MW → 27 MW
    • Current facility power: 25 MW → 38 MW
    Source: Epoch AI
  51. Apr 29, 2024
    Google Bristow · VA
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.
    Source: Epoch AI
  52. Apr 1, 2024
    QTS Richmond 3 · VA
    • Construction started: Land clearing begins.
    Source: Epoch AI
  53. Jan 31, 2024
    CoreWeave Chester VA · VA
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1's second data hall scheduled to come online this month.
    Source: Epoch AI
  54. Jan 29, 2024
    QTS Richmond 1 · VA
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 (retrofitted) is operational. This is based on it looking complete, and cooling towers possibly showing water vapor plumes, in this Google Earth image. Building 2 has chillers added to the roof and perimete…
    Source: Epoch AI
  55. 2024
    Equinix Ashburn DC18 · VA
    • Permit / site plan approved: Loudoun County site plan EPLAN-2024-0193 — Approved, 161,950 sq ft proposed.
  56. 2024
    Equinix DC22 · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0047 — Active, 96,842 sq ft proposed.
  57. 2024
    Proposed data center — Beaumeade · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0047 — Active, 96,842 sq ft proposed.
  58. 2024
    Proposed data center — Beaumeade · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0077 — Active, 1,176,000 sq ft proposed.
  59. 2024
    Proposed data center — Broad Run Business Center · VA
    • Permit / site plan approved: Loudoun County site plan EPLAN-2024-0155 — Approved: Conditionally, 600,742 sq ft proposed.
  60. 2024
    Proposed data center — Commonwealth Center · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0105 — Active, 285,322 sq ft proposed.
  61. 2024
    Proposed data center — Concorde Industrial Park · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0002 — Active, 449,311 sq ft proposed.
  62. 2024
    Proposed data center — Crosstrail Industrl Land Condo · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0211 — Active, 304,794 sq ft proposed.
  63. 2024
    Proposed data center — Digital Dulles Land Condo · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0060 — Active, 4,355,759 sq ft proposed.
  64. 2024
    Proposed data center — Downs Park · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0041 — Active, 1,751,803 sq ft proposed.
  65. 2024
    Proposed data center — Dulles Trade Center 2 · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0042 — Active, 835,330 sq ft proposed.
  66. 2024
    Proposed data center — EPLAN-2024-0058 · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0058 — Active, 256,550 sq ft proposed.
  67. 2024
    Proposed data center — EPLAN-2024-0163 · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0163 — Active, 106,332 sq ft proposed.
  68. 2024
    Proposed data center — EPLAN-2024-0205 · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0205 — Active, 1,239,000 sq ft proposed.
  69. 2024
    Proposed data center — EPLAN-2024-0212 · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0212 — Active, 401,050 sq ft proposed.
  70. 2024
    Proposed data center — Farah Naples · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0184 — Active, 101,092 sq ft proposed.
  71. 2024
    Proposed data center — Gateway North · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0178 — Active, 76,275 sq ft proposed.
  72. 2024
    Proposed data center — Holiday Center · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0056 — Active, 973,305 sq ft proposed.
  73. 2024
    Proposed data center — LEGI-2024-0037 · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0037 — Active, 444,307 sq ft proposed.
  74. 2024
    Proposed data center — LEGI-2024-0039 · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0039 — Active, 1,359,153 sq ft proposed.
  75. 2024
    Proposed data center — Loudoun Business Park · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0030 — Active, 666,000 sq ft proposed.
  76. 2024
    Proposed data center — Loudoun Tech Center · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0058 — Active, 196,138 sq ft proposed.
  77. 2024
    Proposed data center — Mercure Business Park · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0161 — Active, 76,020 sq ft proposed.
  78. 2024
    Proposed data center — Mercure Business Park · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0162 — Active, 178,648 sq ft proposed.
  79. 2024
    Proposed data center — Mercure Business Park · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0180 — Active, 101,579 sq ft proposed.
  80. 2024
    Proposed data center — Mercure Business Park · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0181 — Active, 104,556 sq ft proposed.
  81. 2024
    Proposed data center — Mercure Business Park · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0210 — Active, 48,120 sq ft proposed.
  82. 2024
    Proposed data center — Mid Dulles Center · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0154 — Active, 374,670 sq ft proposed.
  83. 2024
    Proposed data center — Paragonpark · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0200 — Active, 768,255 sq ft proposed.
  84. 2024
    Proposed data center — Prologis Exchange · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0036 — Active, 697,500 sq ft proposed.
  85. 2024
    Proposed data center — Prologis Park Gateway · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0004 — Active, 1,089,044 sq ft proposed.
  86. 2024
    Proposed data center — Spring Valley Farms · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0074 — Active, 3,250,000 sq ft proposed.
  87. 2024
    Proposed data center — Steeplechase · VA
    • Permit / site plan approved: Loudoun County site plan EPLAN-2024-0081 — Approved: Conditionally, 244,400 sq ft proposed.
  88. 2024
    Proposed data center — Sterling Park Ip · VA
    • Permit / site plan filed: Loudoun County site plan EPLAN-2024-0182 — Active, 52,744 sq ft proposed.
  89. 2024
    Proposed data center — Summit At Dulles · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0061 — Active, 592,772 sq ft proposed.
  90. 2024
    Proposed data center — TLREZN2024-0003 · VA
    • Permit / site plan filed: Loudoun County site plan TLREZN2024-0003 — Active, 825,500 sq ft proposed.
  91. 2024
    Proposed data center — Tuscarora Crossing Lb1 Ph1 · VA
    • Permit / site plan approved: Loudoun County site plan EPLAN-2024-0059 — Approved: Conditionally, 520,950 sq ft proposed.
  92. 2024
    Proposed data center — Uss Industrial Park · VA
    • Permit / site plan filed: Loudoun County site plan LEGI-2024-0003 — Active, 2,275,600 sq ft proposed.
  93. Oct 20, 2023
    QTS Manassas DC2 · VA
    • Land acquired: Deed recorded for parcel 7695-48-5650 (owner of record: Qts Manassas I Dc2 LLC).
  94. Oct 20, 2023
    QTS Manassas DC3 · VA
    • Land acquired: Deed recorded for parcel 7695-58-1491 (owner of record: Qts Manassas I Dc3 LLC C/O Blackstone Property Advisors).
  95. Oct 4, 2023
    Digital Realty IAD30 · VA
    • Land acquired: Deed/transfer recorded for parcel 0332 01 0010D: $43,000,000.
  96. Oct 4, 2023
    H5 IAD31 · VA
    • Land acquired: Deed/transfer recorded for parcel 0332 01 0010D: $43,000,000.
  97. Oct 4, 2023
    H5 IAD32 · VA
    • Land acquired: Deed/transfer recorded for parcel 0332 01 0010D: $43,000,000.
  98. Oct 1, 2023
    QTS Richmond 1 · VA
    • Construction started: Land cleared for site expansion, some materials down at substation site. We assume that Buildings 1 and 2 are not running AI workloads at this point due to the lack of cooling infrastructure.
    Source: Epoch AI