DC
/

Georgia

Facilities
58
3 campuses
Power online
923 MW
3 sites reporting
Under construction
0 MW
planned MW at active sites
Planned
—
0 planned sites (MW not disclosed)
AI campuses
3
923 MW online · 0 MW pipeline
AI compute
0.81M
H100-equivalents (est.)
Capital (reported + est.)
$25.9B

Totals only include facilities with a reported or estimated figure; most sites don't disclose power, so these are floors, not market size estimates. Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Average industrial electricity price: 10.03¢/kWh (EIA).

AI data center capacity over time

Facility power at satellite-tracked AI campuses (Epoch AI timelines), quarterly

0 MW250 MW500 MW750 MW1 GW20252026202720282029
Observed (satellite-tracked) Projected

Construction pipeline by expected completion

MW from phases with a projected completion date

No dated pipeline yet.

Power reality

Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.

  • Announced—
  • Interconnection requests—
  • Contracted / approved—
  • Under construction—
  • Operational923 MW
Pending MW by time to power

Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.

Largest gaps: announced vs documented

No large gaps in this scope.

Verified operating: 3Unverified: 55

Markets

Click through to drill down

Online Under construction + planned
NameFacilitiesOnlinePipeline
Atlanta51883 MW—

Largest operators & owners

Online + pipeline MW at linked facilities

Online Under construction + planned

Largest customers & end users

Tenants and workload owners, where sourced

Online Under construction + planned

Utility exposure

Most likely retail utility by location (approximate)

Online Under construction + planned

Grid operators (ISO / RTO)

By facility location

Online Under construction + planned
  • None (non-RTO region)923 MW + 0 MW · 58 sites

Largest facilities

By online + pipeline MW

FacilityStatusOnlinePipeline
Microsoft Fairwater AtlantaOperating859 MW—
CoreWeave Dalton 1 & 2Operating40 MW—
xAI QTS AtlantaOperating24 MW—

Facilities by status

  • Operating58