What changed
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.
Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned
- Oct 31, 2026Anthropic Lake Mariner · NY
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 42 MW → 210 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 49 MW → 245 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Compute (H100-equivalents): 58,600 → 292,800
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Capital cost / investment: $1.6B → $8B
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 1 → 2
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 2 (AKA CB4) is operational. On February 26, Terawulf stated that CB4 was expected to be energized by Q3 2026.
Source: Epoch AI - Oct 26, 2026Equinix Ashburn DC18 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0027: Active → Site plan EPLAN-2024-0193: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 183,900 sq ft → 162,000 sq ft
- Oct 26, 2026Meta Los Lunas · NM
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 87 MW → 118 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 114 MW → 147 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Compute (H100-equivalents): 99,500 → 133,900
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Capital cost / investment: $3.3B → $4.5B
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 1 → 2
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
Source: Epoch AI - Oct 26, 2026Proposed data center — Beaumeade · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2024-0047 : Active → Site plan EPLAN-2023-0083: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 96,800 sq ft → 113,000 sq ft
- Oct 26, 2026Proposed data center — EPLAN-2025-0195 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2023-0048: Approved → Site plan EPLAN-2025-0195: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 67,800 sq ft → 751,900 sq ft
- Oct 26, 2026Proposed data center — Loudoun Tech Center · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan STPL-2023-0008: Approved: Conditionally → Site plan LEGI-2024-0058: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 285,200 sq ft → 196,100 sq ft
- Oct 26, 2026Proposed data center — Prologis Exchange · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan EPLAN-2024-0036: Active → Site plan EPLAN-2025-0102: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 697,500 sq ft → 16,000 sq ft
- Oct 26, 2026Proposed data center — Sdc Ashburn · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0015: Active → Site plan STMP-2022-0020: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 20,000 sq ft → 621,500 sq ft
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Operating → Under construction
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Floor area: 531,600 sq ft → 1.06M sq ft
- Oct 19, 2026Anthropic-Amazon New Carlisle · IN
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 910 MW → 1.04 GW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 1.09 GW → 1.24 GW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Compute (H100-equivalents): 685,900 → 818,400
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Capital cost / investment: $34.5B → $39.3B
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 16 → 18
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to a…
Source: Epoch AI - Oct 19, 2026Equinix Ashburn DC18 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0027: Active → Site plan EPLAN-2024-0193: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 183,900 sq ft → 162,000 sq ft
- Oct 19, 2026Proposed data center — Beaumeade · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2024-0047 : Active → Site plan EPLAN-2023-0083: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 96,800 sq ft → 113,000 sq ft
- Oct 19, 2026Proposed data center — EPLAN-2025-0195 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2023-0048: Approved → Site plan EPLAN-2025-0195: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 67,800 sq ft → 751,900 sq ft
- Oct 19, 2026Proposed data center — Loudoun Tech Center · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan STPL-2023-0008: Approved: Conditionally → Site plan LEGI-2024-0058: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 285,200 sq ft → 196,100 sq ft
- Oct 19, 2026Proposed data center — Prologis Exchange · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan EPLAN-2024-0036: Active → Site plan EPLAN-2025-0102: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 697,500 sq ft → 16,000 sq ft
- Oct 19, 2026Proposed data center — Sdc Ashburn · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0015: Active → Site plan STMP-2022-0020: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 20,000 sq ft → 621,500 sq ft
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Operating → Under construction
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Floor area: 531,600 sq ft → 1.06M sq ft
- Oct 14, 2026Amazon Web Services CMH50 · OH
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 095-111744-00.000 (no sale price disclosed).
Source: Licking County, OH — Auditor - Oct 14, 2026Amazon Web Services CMH53 · OH
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 095-111744-00.000 (no sale price disclosed).
Source: Licking County, OH — Auditor - Oct 14, 2026Amazon Web Services CMH59 · OH
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 095-111744-00.000 (no sale price disclosed).
Source: Licking County, OH — Auditor - Oct 14, 2026Amazon Web Services CMH56 · OH
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 095-111744-00.000 (no sale price disclosed).
Source: Licking County, OH — Auditor - Oct 14, 2026Amazon Web Services CMH62 · OH
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 095-111744-00.000 (no sale price disclosed).
Source: Licking County, OH — Auditor - Oct 14, 2026Lumen McLean · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Last recorded sale price: $52M → $29M
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 0294 06 0104: $29,000,000.
- Oct 12, 2026Argo Data Center · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Operating → Under construction
Source: OpenStreetMap contributors - Oct 12, 2026Equinix Ashburn DC18 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0027: Active → Site plan EPLAN-2024-0193: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 183,900 sq ft → 162,000 sq ft
- Oct 12, 2026Proposed data center — Beaumeade · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2024-0047 : Active → Site plan EPLAN-2023-0083: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 96,800 sq ft → 113,000 sq ft
- Oct 12, 2026Proposed data center — EPLAN-2025-0195 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2023-0048: Approved → Site plan EPLAN-2025-0195: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 67,800 sq ft → 751,900 sq ft
- Oct 12, 2026Proposed data center — Loudoun Tech Center · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan STPL-2023-0008: Approved: Conditionally → Site plan LEGI-2024-0058: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 285,200 sq ft → 196,100 sq ft
- Oct 12, 2026Proposed data center — Prologis Exchange · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan EPLAN-2024-0036: Active → Site plan EPLAN-2025-0102: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 697,500 sq ft → 16,000 sq ft
- Oct 12, 2026Proposed data center — Sdc Ashburn · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0015: Active → Site plan STMP-2022-0020: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 20,000 sq ft → 621,500 sq ft
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Operating → Under construction
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Floor area: 531,600 sq ft → 1.06M sq ft
- Oct 5, 2026Equinix Ashburn DC18 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0027: Active → Site plan EPLAN-2024-0193: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 183,900 sq ft → 162,000 sq ft
- Oct 5, 2026Proposed data center — Beaumeade · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2024-0047 : Active → Site plan EPLAN-2023-0083: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 96,800 sq ft → 113,000 sq ft
- Oct 5, 2026Proposed data center — EPLAN-2025-0195 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2023-0048: Approved → Site plan EPLAN-2025-0195: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 67,800 sq ft → 751,900 sq ft
- Oct 5, 2026Proposed data center — Loudoun Tech Center · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan STPL-2023-0008: Approved: Conditionally → Site plan LEGI-2024-0058: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 285,200 sq ft → 196,100 sq ft
- Oct 5, 2026Proposed data center — Prologis Exchange · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan EPLAN-2024-0036: Active → Site plan EPLAN-2025-0102: Active
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 697,500 sq ft → 16,000 sq ft
- Oct 5, 2026Proposed data center — Sdc Ashburn · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Permitting status: Site plan LEGI-2025-0015: Active → Site plan STMP-2022-0020: Approved
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Planned floor area: 20,000 sq ft → 621,500 sq ft
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Operating → Under construction
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Floor area: 531,600 sq ft → 1.06M sq ft