DC
/

What changed — Ohio

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. May 28, 2026
    Meta Prometheus · OH
    • Land acquired: Deed/transfer recorded for parcel 095-112218-00.000 (no sale price disclosed).
  2. May 18, 2026
    Google New Albany · OH
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  3. May 18, 2026
    Meta Prometheus · OH
    • Current IT capacity: 368 MW → 496 MW
    • Current facility power: 478 MW → 645 MW
    • Buildings operational: 6 → 11
    • New capacity online: Building 7-11 (Meta tents) are operational. In January we saw them look almost complete, with some work still ongoing for power equipment. Assuming 3 more months for commissioning, we expect operation by May. Northern…
    Source: Epoch AI
  4. May 1, 2026
    Google Columbus · OH
    • Current IT capacity: 216 MW → 303 MW
    • Current facility power: 260 MW → 364 MW
    • Buildings operational: 3 → 4
    • New capacity online: Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.
    Source: Epoch AI
  5. Mar 12, 2026
    AWS New Albany · OH
    • Current IT capacity: 113 MW → 213 MW
    • Current facility power: 136 MW → 255 MW
    • Buildings operational: 5 → 9
    • New capacity online: Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, northern campus Buildi…
    Source: Epoch AI
  6. Mar 12, 2026
    Google Lancaster · OH
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  7. Mar 9, 2026
    AWS New Albany · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111408-00.000 (no sale price disclosed).
  8. Jan 18, 2026
    Meta Prometheus · OH
    • Current IT capacity: 76 MW → 368 MW
    • Current facility power: 99 MW → 478 MW
    • Buildings operational: 1 → 6
    • New capacity online: Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their…
    Source: Epoch AI
  9. Dec 2, 2025
    STACK New Albany · OH
    • Land acquired: Deed/transfer recorded for parcel 222-004355 (no sale price disclosed).
  10. Oct 31, 2025
    Google Lancaster · OH
    • Current IT capacity: 68 MW → 137 MW
    • Current facility power: 82 MW → 164 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 operational. This is supported by the state of Building 2 a month prior, which is entirely complete outside of some equipment that was removed later on.
    Source: Epoch AI
  11. Oct 14, 2025
    Google New Albany · OH
    • Current IT capacity: 222 MW → 333 MW
    • Current facility power: 267 MW → 400 MW
    • Buildings operational: 3 → 4
    • New capacity online: Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in place. One cooling…
    Source: Epoch AI
  12. Oct 14, 2025
    Meta Prometheus · OH
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power …
    Source: Epoch AI
  13. Oct 12, 2025
    OpenAI Stargate Lordstown · OH
    • Construction started: Land clearing begins in the front of the site (the side facing the Ohio Turnpike), clearing away a parking lot and solar array
    Source: Epoch AI
  14. Oct 1, 2025
    Google Columbus · OH
    • Current IT capacity: 130 MW → 216 MW
    • Current facility power: 156 MW → 260 MW
    • Buildings operational: 2 → 3
    • New capacity online: Building 3 operational. Surrounding roads finished, no more visible construction.
    Source: Epoch AI
  15. Jun 1, 2025
    Google New Albany · OH
    • Current IT capacity: 144 MW → 222 MW
    • Current facility power: 173 MW → 267 MW
    • Buildings operational: 2 → 3
    • New capacity online: Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on Building 5 - some…
    Source: Epoch AI
  16. Apr 9, 2025
    AWS New Albany · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111756-00.024 (no sale price disclosed).
  17. Mar 1, 2025
    Google Columbus · OH
    • Current IT capacity: 65 MW → 130 MW
    • Current facility power: 78 MW → 156 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 operational. Parking complete, no more visible construction.
    Source: Epoch AI
  18. Feb 13, 2025
    AWS New Albany · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111648-00.000 (no sale price disclosed).
  19. Dec 1, 2024
    AWS New Albany · OH
    • Buildings operational: 0 → 5
    • Status: Under construction → Operating + expanding
    • New capacity online: Buildings 5-9 (eastern campus) operational. New Albany’s Dec. 2024 report lists AWS partial occupancy for 5 buildings at the eastern campus. Note that we're only including roughly 44% of all the New Albany campuses IT…
    Source: Epoch AI
  20. Nov 1, 2024
    Meta Bowling Green · OH
    • Construction started: Land clearing begins.
    Source: Epoch AI
  21. Sep 13, 2024
    Google New Albany · OH
    • Current IT capacity: 67 MW → 144 MW
    • Current facility power: 80 MW → 173 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Building 3 roof is also…
    Source: Epoch AI
  22. Aug 20, 2024
    Vantage Building 1 · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111756-00.009 (no sale price disclosed).
  23. Aug 20, 2024
    Vantage Building 2 · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111756-00.009 (no sale price disclosed).
  24. Aug 20, 2024
    Vantage Building 3 · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111756-00.009 (no sale price disclosed).
  25. Aug 15, 2024
    Amazon Web Services · OH
    • Land acquired: Deed/transfer recorded for parcel 050-002806 (no sale price disclosed).
  26. Aug 15, 2024
    Amazon Web Services · OH
    • Land acquired: Deed/transfer recorded for parcel 050-002806 (no sale price disclosed).
  27. Aug 15, 2024
    Unnamed data center · OH
    • Land acquired: Deed/transfer recorded for parcel 050-002806 (no sale price disclosed).
  28. Aug 15, 2024
    Unnamed data center · OH
    • Land acquired: Deed/transfer recorded for parcel 050-002806 (no sale price disclosed).
  29. Jun 6, 2024
    QTS NAL 2 DC1 · OH
    • Land acquired: Deed/transfer recorded for parcel 094-107502-00.003 (no sale price disclosed).
  30. Jun 6, 2024
    QTS NAL 2 DC2 · OH
    • Land acquired: Deed/transfer recorded for parcel 094-107502-00.004 (no sale price disclosed).
  31. Jun 6, 2024
    QTS NAL1 DC1 · OH
    • Land acquired: Deed/transfer recorded for parcel 094-106404-00.011 (no sale price disclosed).
  32. Jun 6, 2024
    QTS NAL1 DC2 · OH
    • Land acquired: Deed/transfer recorded for parcel 094-106404-00.010 (no sale price disclosed).
  33. Apr 20, 2024
    Google New Albany · OH
    • Construction started: Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete.
    Source: Epoch AI
  34. Apr 1, 2024
    Google Columbus · OH
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.
    Source: Epoch AI
  35. Jan 1, 2024
    Google Lancaster · OH
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 operational. This is estimated based on construction progress in October 2023. This also corresponds to a 2023 article where a Google spokesperson says that the "the Lancaster data center will open later th…
    Source: Epoch AI
  36. Dec 21, 2023
    Amazon Web Services · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111618-04.000 (no sale price disclosed).
  37. Dec 21, 2023
    Amazon Web Services · OH
    • Land acquired: Deed/transfer recorded for parcel 095-111618-04.000 (no sale price disclosed).