Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. Aug 30, 2026
    Coreweave Helios · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/…
    Source: Epoch AI
  2. Jul 3, 2026
    CoreWeave Denton TX · TX
    • Current IT capacity: 131 MW → 262 MW
    • Current facility power: 183 MW → 367 MW
    • Buildings operational: 4 → 7
    • New capacity online: Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.
    Source: Epoch AI
  3. Jul 1, 2026
    Google Midlothian · TX
    • Current IT capacity: 69 MW → 103 MW
    • Current facility power: 82 MW → 123 MW
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  4. May 23, 2026
    OpenAI Stargate Abilene · TX
    • Current IT capacity: 211 MW → 421 MW
    • Current facility power: 295 MW → 590 MW
    • Buildings operational: 2 → 4
    • New capacity online: Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 …
    Source: Epoch AI
  5. Apr 19, 2026
    Google Midlothian · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is probably mostly operational despite some cooling towers yet to be installed. In the original building permit Google only expected to build 6 new cooling towers, but they've extended the row further. This…
    Source: Epoch AI
  6. Mar 31, 2026
    Microsoft SAT14 · TX
    • Current IT capacity: 19 MW → 47 MW
    • Current facility power: 26 MW → 66 MW
    • Buildings operational: 1 → 2
    • Status: Operating + expanding → Operating
    • New capacity online: Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the si…
    Source: Epoch AI
  7. Feb 23, 2026
    CoreWeave Denton TX · TX
    • Current IT capacity: 67 MW → 131 MW
    • Current facility power: 94 MW → 183 MW
    • Buildings operational: 3 → 4
    • New capacity online: Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction.…
    Source: Epoch AI
  8. Feb 15, 2026
    Vantage TX1 · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, bas…
    Source: Epoch AI
  9. Feb 4, 2026
    Microsoft SAT40 · TX
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  10. Dec 31, 2025
    CoreWeave Denton TX · TX
    • Current IT capacity: 8 MW → 67 MW
    • Current facility power: 11 MW → 94 MW
    • Buildings operational: 1 → 3
    • New capacity online: Half the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings.
    Source: Epoch AI
  11. Dec 24, 2025
    OpenAI Stargate Abilene · TX
    • Current IT capacity: 105 MW → 211 MW
    • Current facility power: 147 MW → 295 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also cons…
    Source: Epoch AI
  12. Dec 9, 2025
    Meta Temple · TX
    • Buildings operational: 0 → 2
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best estimate, but note that the planned co…
    Source: Epoch AI
  13. Dec 1, 2025
    Microsoft SAT40 · TX
    • Current IT capacity: 47 MW → 75 MW
    • Current facility power: 66 MW → 106 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 operational. No more construction on building, and surrounding roads are also complete.
    Source: Epoch AI
  14. Nov 2, 2025
    Crusoe Abilene Expansion · TX
    • Construction started: Land clearing begins for Buildings 1-2.
    Source: Epoch AI
  15. Sep 27, 2025
    OpenAI Stargate Milam · TX
    • Construction started: Land clearing begins for the site
    Source: Epoch AI
  16. Sep 26, 2025
    OpenAI Stargate Abilene · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm t…
    Source: Epoch AI
  17. Sep 18, 2025
    Anthropic Barber Lake · TX
    • Construction started: Site grading and civil works begin.
    Source: Epoch AI
  18. Aug 25, 2025
    Google Red Oak · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is operational, based on a Google Earth image showing a completed building shell and equipment, and the large construction car park being emptied. Building 2 shell looks mostly completed.
    Source: Epoch AI
  19. Aug 1, 2025
    OpenAI Stargate Shackelford · TX
    • Construction started: Land clearing begins.
    Source: Epoch AI
  20. May 31, 2025
    CoreWeave Denton TX · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: First 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter.
    Source: Epoch AI
  21. May 31, 2025
    Coreweave Helios · TX
    • Construction started: The former crypto mining Helios site begins expanding, with land cleared for additional buildings.
    Source: Epoch AI
  22. May 19, 2025
    Goodnight · TX
    • Construction started: Land clearing begins
    Source: Epoch AI
  23. Nov 1, 2024
    CoreWeave Denton TX · TX
    • Construction started: Construction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy C…
    Source: Epoch AI
  24. Jul 1, 2024
    Microsoft SAT14 · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously inc…
    Source: Epoch AI
  25. May 31, 2024
    OpenAI Stargate Abilene · TX
    • Construction started: Land clearing begins for northern two buildings (Building 1-2)
    Source: Epoch AI
  26. May 24, 2024
    Microsoft SAT40 · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 operational. Estimated 3 months out from February, when there was still construction equipment.
    Source: Epoch AI
  27. Dec 15, 2023
    Vantage TX1 · TX
    • Construction started: Land clearing begins for both Building 1 & Building 2
    Source: Epoch AI
  28. Nov 28, 2023
    Google Midlothian · TX
    • Construction started: Visible land clearing around the area for Building 1
    Source: Epoch AI