DC
/

Dataset table

Every tracked facility. Click any value to see its evidence level, date, supporting quote and sources. “—” means not disclosed or not yet collected.

1,954 rows:Download CSVJSONAPI docs
Clear
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned
Data centers, sorted by Power online
FacilityLocationStatusOperator / ownerTenants / usersPower online ↑PlannedSizeUtility · ISOVerificationLast verified
CloudHQ LC14
Colocation
VA
Under constructionEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
CloudHQShow sources
confidence: likely
—
108 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
478,900 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Under constructionSep 27, 2026
CloudHQ LC12
Colocation
Ashburn, VA
Under constructionEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
CloudHQShow sources
confidence: likely
—
108 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
141,600 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Documented developmentSep 27, 2026
CloudHQ LC8
Colocation
Ashburn, VA
Under constructionEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
CloudHQShow sources
confidence: likely
—
108 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
517,600 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Under constructionSep 27, 2026
Meta Gallatin
AI campus
Gallatin, TN
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
114 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Cumberland Elec Member CorpShow sources
confidence: likely
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
CoreWeave Chester VA
AI campus
VA
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 20, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
CoreWeaveShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
114 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 20, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
197 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 20, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
STACK Infrastructure NVA02
AI campus
Manassas, VA
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
118 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
487 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Midlothian
AI campus
Midlothian, TX
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
123 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
United Electric Coop Service INC - (Tx)Show sources
confidence: unverified
ERCOTEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Kansas City East
AI campus
MO
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
126 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Evergy Missouri WestShow sources
confidence: likely
SPPEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
EdgeCore AS01
Unclassified
Sterling, VA
Under constructionEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
EdgeCoreShow sources
confidence: likely
—
126 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
416,100 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Under constructionSep 27, 2026
CloudHQ LC3
Colocation
Ashburn, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
CloudHQShow sources
confidence: likely
—
132 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
585,600 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Digital Realty IAD41
Colocation
Ashburn, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
Digital RealtyShow sources
confidence: likely
—
135 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
789,400 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
AWS Berwick
AI campus
Berwick, PA
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Amazon Web ServicesShow sources
confidence: confirmed

“Last year, Talen announced the sale of its 960 MW Cumulus data centre campus to Amazon Web Services (AWS)”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • World Nuclear News · New supply agreement expands Talen-Amazon partnership - World Nuclear
Amazon Web ServicesShow sources
confidence: likely

“co-located AWS data center at the Susquehanna plant”

  • utilitydive.com · Talen to sell Amazon 1.9 GW from Susquehanna nuclear plant | Utility D
139 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
212 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
PPL Electric UtilitiesShow sources
confidence: confirmed

“Amazon / Data Center Salem Township, PA”

PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 28, 2026
CloudHQ LC2
Colocation
Ashburn, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
CloudHQShow sources
confidence: likely
—
162 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
499,400 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Lancaster
AI campus
Lancaster, OH
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Mar 12, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
164 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Mar 12, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
South Central Power CompanyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Lincoln
AI campus
Lincoln, NE
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 12, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
170 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 12, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
339 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 12, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Lincoln Electric SystemShow sources
confidence: unverified
SPPEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Eagle Mountain
AI campus
Eagle Mountain, UT
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 2, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
179 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 2, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
PacifiCorpShow sources
confidence: likely
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Cheyenne
AI campus
WY
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 25, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
182 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 25, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
249 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 25, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
635,300 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Black Hills EnergyShow sources
confidence: confirmed

“Meta / Data Center Cheyenne, WY ▪ $800 million data center project.”

None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 28, 2026
Google The Dalles
AI campus
OR
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 29, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
185 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 29, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Northern Wasco County PudShow sources
confidence: unverified
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Digital Realty IAD39
Colocation
Ashburn, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
Digital RealtyShow sources
confidence: likely
—
192 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
1.54M sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Kuna
AI campus
ID
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
198 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
686,100 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Idaho PowerShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Temple
AI campus
Temple, TX
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 24, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
198 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 24, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
231 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 24, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
666,600 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Pedernales Electric Coop, INCShow sources
confidence: unverified
ERCOTEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Huntsville
AI campus
AL
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 2, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
198 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 2, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
669,000 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Tennessee Valley AuthorityShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Montgomery
AI campus
Montgomery, AL
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
199 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
465 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Alabama Power COShow sources
confidence: likely
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Coreweave Helios
AI campus
Afton, TX
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 30, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
CoreWeave, Galaxy Digital Inc.Show sources
confidence: confirmed

“Galaxy Digital Inc. (Nasdaq: GLXY ) (the "Company" or "Galaxy"), a global leader in digital assets and data center infrastructure, today announced that it has completed delivery of the first phase of power at its Helios data center campus”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • prnewswire.com · Galaxy Completes Phase I of Its Helios Data Center Campus, Delivering
CoreWeaveShow sources
confidence: likely

“delivering approximately 200 megawatts ("MW") of gross power — 133 MW of critical IT load — to CoreWeave”

  • prnewswire.com · Galaxy Completes Phase I of Its Helios Data Center Campus, Delivering
200 MWAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.Show sources
AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.confidence: likelyas of Aug 30, 2026

“approximately 200 megawatts ("MW") of gross power”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • prnewswire.com · Galaxy Completes Phase I of Its Helios Data Center Campus, Delivering
800 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 30, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
South Plains Electric Coop INCShow sources
confidence: unverified
ERCOTEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
QTS Richmond 3
AI campus
Sandston, VA
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
202 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
336 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Dominion EnergyShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Storey County
AI campus
NV
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 13, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
214 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 13, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
389 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 13, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
NV EnergyShow sources
confidence: likely
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Microsoft Project Osmium
AI campus
Cumming, IA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 16, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MicrosoftShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
228 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 16, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
MidAmerican EnergyShow sources
confidence: unverified
MISOEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Mesa
AI campus
AZ
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
237 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
287,400 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Salt River ProjectShow sources
confidence: unverified
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Rosemount
AI campus
Rosemount, MN
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 19, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
241 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 19, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
602,200 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Northern States Power CO - MinnesotaShow sources
confidence: likely
MISOEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Jeffersonville
AI campus
Jeffersonville, IN
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 4, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
241 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 4, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Duke EnergyShow sources
confidence: unverified
MISOEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta-QTS Hillsboro 2
AI campus
Hillsboro, OR
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 17, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: likely
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: likely
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
243 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 17, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Portland General ElectricShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
QTS Richmond 2
AI campus
Sandston, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
252 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Dominion EnergyShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
AWS New Albany
AI campus
OH
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Amazon Web ServicesShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
255 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
405 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
American Electric PowerShow sources
confidence: unverified
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Microsoft Goodyear
AI campus
Goodyear, AZ
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 27, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MicrosoftShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Microsoft, OpenAIShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
263 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Apr 27, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Salt River ProjectShow sources
confidence: unverified
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
CloudHQ LC1
Colocation
Ashburn, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
CloudHQShow sources
confidence: likely
—
264 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
984,100 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
CloudHQ LC4
Colocation
Ashburn, VA
Under constructionEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: confirmedas of Sep 27, 2026
CloudHQShow sources
confidence: likely
—
270 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
—
616,700 sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
Dominion EnergyShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Under constructionSep 27, 2026
Amazon Ridgeland
AI campus
MS
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Amazon Web ServicesShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
273 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
1.01 GWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
EntergyShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MISOEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Council Bluffs (East)
AI campus
Council Bluffs, IA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 7, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
284 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 7, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
MidAmerican EnergyShow sources
confidence: likely
MISOEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Omaha
AI campus
Omaha, NE
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 30, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
284 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 30, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
474 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 30, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Omaha Public Power DistrictShow sources
confidence: likely
SPPEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Papillion
AI campus
NE
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 4, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
284 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 4, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Omaha Public Power DistrictShow sources
confidence: likely
SPPEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Bristow
AI campus
Bristow, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 20, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Google DeepMindShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
286 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 20, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Dominion EnergyShow sources
confidence: unverified
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
QTS Richmond 1
AI campus
Sandston, VA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 13, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
333 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Feb 13, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Dominion EnergyShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Amazon Madison Mega Site
AI campus
MS
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 4, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Amazon Web ServicesShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
341 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 4, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
819 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 4, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
1.07M sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
EntergyShow sources
confidence: unverified
MISOEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Columbus
AI campus
Columbus, OH
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 5, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
364 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 5, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
464 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 5, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
1.17M sq ftConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Show sources
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.confidence: confirmedas of Sep 27, 2026
American Electric PowerShow sources
confidence: likely
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
CoreWeave Denton TX
AI campus
Denton, TX
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
CoreWeaveShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
OpenAIShow sources
confidence: likely
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
367 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
395 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 1, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Denton County Elec Coop, INCShow sources
confidence: unverified
ERCOTEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google New Albany
AI campus
New Albany, OH
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
400 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 18, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
95,300 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
American Electric PowerShow sources
confidence: unverified
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Colossus 1
AI campus
Memphis, TN
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
SpaceXAI (xAI)Show sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
AnthropicShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
425 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
442 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Memphis Light, Gas and WaterShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Google Pryor (North)
AI campus
Pryor, OK
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 6, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
GoogleShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
442 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 6, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Public Service CO of OklahomaShow sources
confidence: unverified
SPPEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Microsoft Fairwater Wisconsin
AI campus
Mount Pleasant, WI
Operating + expandingAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.Show sources
AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.confidence: confirmedas of Jun 23, 2026

“the second is scheduled to be completed in 2028”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • Microsoft · Microsoft completes construction on first datacenter facility in Mount
MicrosoftShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
OpenAI, MicrosoftShow sources
confidence: likely
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
442 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
2.72 GWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of May 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
1.2M sq ftAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.Show sources
AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.confidence: confirmedas of Sep 18, 2025

“a combined 1.2 million square feet under roofs”

  • Microsoft · Inside the world's most powerful AI datacenter
We EnergiesShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MISOEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
OpenAI Stargate Abilene
AI campus
Abilene, TX
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 28, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Oracle, CrusoeShow sources
confidence: confirmed

“Crusoe Announces Flagship Abilene Data Center is Live”

“Designed and built by Crusoe at the Lancium Clean Campus”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • Crusoe · Crusoe Announces Flagship Abilene Data Center is Live
  • Crusoe · Crusoe expands Abilene AI campus to 1.2 GW | Crusoe
OpenAI, OracleShow sources
confidence: confirmed

“Oracle Cloud Infrastructure (OCI)”

“first phase of Stargate's flagship data center campus in Abilene, Texas”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • Crusoe · Crusoe Announces Flagship Abilene Data Center is Live
590 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 28, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
1.18 GWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jul 28, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
4M sq ftAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.Show sources
AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.confidence: likelyas of Mar 18, 2025

“approximately 4 million square feet”

  • Crusoe · Crusoe expands Abilene AI campus to 1.2 GW | Crusoe
American Electric PowerShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
ERCOTEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Meta Prometheus
AI campus
New Albany, OH
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 31, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MetaShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
645 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 31, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
1.33 GWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Aug 31, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
95,300 sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
American Electric PowerShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Microsoft Fairwater Atlanta
AI campus
Fayetteville, GA
OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
MicrosoftShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
OpenAI, MicrosoftShow sources
confidence: likely
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
859 MWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 14, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
——
Georgia PowerShow sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Anthropic-Amazon New Carlisle
AI campus
New Carlisle, IN
OperatingAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.Show sources
AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.confidence: likelyas of Oct 29, 2025

“The $11 billion facility is up and operational”

  • CNBC · Amazon opens $11 billion AI data center Project Rainier in Indiana
Amazon Web ServicesShow sources
confidence: confirmed

“Amazon has opened a data center on 1,200 acres of land in Indiana”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • CNBC · Amazon opens $11 billion AI data center Project Rainier in Indiana
AnthropicShow sources
confidence: confirmed

“dedicated to training and running models from Anthropic”

“The complex was built exclusively to train and run models from Anthropic.”

  • Epoch AI · AI data centers (Frontier Data Centers Hub)
  • CNBC · Amazon opens $11 billion AI data center Project Rainier in Indiana
1.09 GWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 3, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
2.2 GWAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.Show sources
AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.confidence: confirmedas of Oct 29, 2025

“draw more than 2.2 gigawatts of electricity”

  • CNBC · Amazon opens $11 billion AI data center Project Rainier in Indiana
1.47M sq ftEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Sep 27, 2026
Indiana Michigan Power (AEP)Show sources
confidence: likely

“working with American Electric Power through its Indiana Michigan Power subsidiary”

“Indiana Michigan Power is in the final stages of acquiring a natural gas plant in Oregon, Ohio, that would make up 15% of the utility’s power by the end of 2026 and help power the AWS AI data center in New Carlisle, Indiana.”

  • CNBC · Amazon opens $11 billion AI data center Project Rainier in Indiana
PJMEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026
Colossus 2
AI campus
Memphis, TN
Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
SpaceXAI (xAI)Show sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
Anthropic, Cursor +1Show sources
confidence: confirmed
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
1.28 GWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
2.07 GWEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likelyas of Jun 15, 2026
  • Epoch AI · AI data centers (Frontier Data Centers Hub)
—
Memphis Light, Gas and WaterShow sources
confidence: unverified
None (non-RTO region)EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Show sources
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.confidence: likely
Verified operatingSep 27, 2026